UKStrait of Hormuz Traffic Halves After US-Iran Strikes and Deal CollapseFRUne femme tuée par balle à Champforgeuil, son compagnon se rend à la policeCN高雄市應對巴威颱風:水公司調降澄清湖水位,水利局排空滯洪池BRServidores do RJ relatam descontos duplicados e abusivos após liquidação do Banco MasterTRPolonya Dışişleri Bakanı Sikorski: Rusya bize karşı hibrit savaş yürütüyorRUРоссия в ООН: Европе безразлично количество жертв на Украине и в РоссииBRFesta do Peão de Salto de Pirapora tem Zezé Di Camargo e Henrique & Diego nesta quinta-feiraITNorvegia ai quarti dei Mondiali: il 'modello' che punta su bambini felici e non vincentiJPトランプ大統領、NATO会議を「大成功」と評価、態度一転に周囲驚くCN「巴威」颱風影響 金門小三通七月十日停航一天UKStrait of Hormuz Traffic Halves After US-Iran Strikes and Deal CollapseFRUne femme tuée par balle à Champforgeuil, son compagnon se rend à la policeCN高雄市應對巴威颱風:水公司調降澄清湖水位,水利局排空滯洪池BRServidores do RJ relatam descontos duplicados e abusivos após liquidação do Banco MasterTRPolonya Dışişleri Bakanı Sikorski: Rusya bize karşı hibrit savaş yürütüyorRUРоссия в ООН: Европе безразлично количество жертв на Украине и в РоссииBRFesta do Peão de Salto de Pirapora tem Zezé Di Camargo e Henrique & Diego nesta quinta-feiraITNorvegia ai quarti dei Mondiali: il 'modello' che punta su bambini felici e non vincentiJPトランプ大統領、NATO会議を「大成功」と評価、態度一転に周囲驚くCN「巴威」颱風影響 金門小三通七月十日停航一天
Newsgather
BackBombay HC Orders Builder to Pay 10.05% Interest for Delayed Home Deliveries
Bombay HC Orders Builder to Pay 10.05% Interest for Delayed Home Deliveries
NOTICIA
Economic Times11.06.2026Law3 dk okumaIndia

Bombay HC Orders Builder to Pay 10.05% Interest for Delayed Home Deliveries

En resumen

  • The Bombay High Court ordered a Mumbai builder to pay 10.05% annual interest to homebuyers for significant delays in delivering flats booked nearly two decades ago.
  • The court emphasized builders cannot indefinitely hold buyers' money and highlighted the vulnerable position of homebuyers.

Resumen generado por IA

Por qué importa

Several homebuyers booked flats in a Mumbai housing project between 2005-2007, with possession promised between 2008-2010. Nearly two decades later, they are still awaiting their homes, having paid 50-60% of the amount.

Tamaño de fuente

With the hope of having their own roof over their heads in Mumbai, several homebuyers booked flats in a housing project launched in 2005-2006. Nearly two decades later, they are still awaiting possession, which was originally promised between 2008 and 2010.

The Bombay High Court, however, recently offered some relief to these distressed homebuyers, many of whom have already paid 50-60% of the amount to the developer for the flats. “Even after a period of almost 20 years of execution of agreement and after lapse of about 16 years from the agreed date of handing over possession, the possession has not been given,” the HC observed.

The Bombay High Court, in its ruling, said a builder can’t indefinitely retain purchasers’ money while failing to deliver homes. For the delay, the HC ordered the Mumbai-based builder to pay interest at 10.05% per annum from February 1, 2014, to the buyers until the possession is handed over.

In addition, the Bombay HC imposed costs of Rs 1 lakh each on the developer in two appeals and Rs 10,000 each in eight other appeals, directing the amount to be paid within four weeks.

High Court rules in favour of Mumbai homebuyers: What is the case about?

The case pertains to delay in possession of flats in a housing project in Nahur, Mulund (a Mumbai suburb). Several allottees had booked flats in the project between 2005 and 2007, costing from Rs 36.32 lakh to Rs 60.75 lakh.

While homebuyers were promised possession between 2008 and 2010, the flats are yet to be handed over to them even after nearly two decades.

Amid the delay, homebuyers first approached the MahaREAT, and consequently, they moved to the Bombay High Court.

Hearing the case, the Bombay High Court dismissed the builder’s contention and highlighted that “under Section 18(1) and its proviso, the homebuyers, who chose not to withdraw from the project, are unconditionally entitled to interest for every month of delay until possession is actually delivered.”

The HC explained how the homebuyer is in a very vulnerable position as he borrows money to pay for a house and “simultaneously plays the role of a financer as building projects collect money upfront.” This makes the buyer the weakest stakeholder with a high financial exposure.

Interest payment to homebuyers for delayed possession

In this case, the Bombay HC upheld the MahaREAT’s 2018 order, which ordered the developer to pay 10.05% annual interest to homebuyers for delayed possession. The Tribunal had directed the builder to pay interest to buyers from February 1, 2014, until actual possession was handed over.

The high court held that homebuyers have an unqualified right to get interest every month for delayed possession under the Real Estate (Regulation and Development) Act (RERA).

Forest land behind the 20-year delay?

According to the developer, forest land and other issues were the primary reasons for the delay in project completion. The builder’s lawyers argued that large areas of Mulund had come under forest reservation in 2006 and indicated that they had filed a writ petition before the Bombay HC challenging the mutation entry inserted by the City Survey Officer in the property card register.

As per the City Survey Officer’s entry, “the land is the forest land, and no development/construction will be allowed unless NOC from the forest department is obtained in respect of the said land.”

For now, the Bombay High Court has ruled in favour of the homebuyers who have been waiting to secure possession of their flats booked nearly two decades ago. HC further underlined that RERA was enacted with an object to ensure greater accountability towards consumers, significantly reduce fraud, delays, and the high transaction costs, and balance the interests of consumers and promoters by imposing certain responsibilities on both.

(Join our ETWealth WhatsApp channel for all the latest updates)

Qué observar

Perspectiva de IA — posibilidades, no hechos

  • The builder will likely appeal the Bombay High Court's decision or seek to negotiate a settlement with the homebuyers.

    Posible · En semanas

  • Further legal action may be taken by homebuyers if possession is not delivered promptly after the interest payment order.

    Probable · En meses

Preguntas abiertas

  • When will the builder finally deliver possession of the flats?
  • What specific actions will the builder take to expedite the project completion?
  • Will the builder face further penalties if possession is not delivered within a new timeframe?
  • How many other projects by this builder are facing similar delays?