CN台南全面追查問題油品,市長黃偉哲要求涉案產品全下架CN資深媒體人矢板明夫演講後遇襲,檢方認定涉境外勢力指使聲押被告ARمونديال 2026: الأرجنتين تواجه مصر وسويسرا تواجه كولومبيا في مواجهات حاسمةINTLIndia News Roundup: Landslide in Kerala, Soldier Ambush in Manipur, Missile Deal with IndonesiaDEJosef Hecken: "Ich habe mich oft unbeliebt gemacht"RUЛавров: Россия рассчитывает на участие главы комиссии Афросоюза в саммите Россия-АфрикаCRYPTO-FRMichael Saylor : Le Bitcoin doit-il rester figé pour prospérer ?ARمصر تواجه الأرجنتين في ثمن نهائي كأس العالم: صلاح ضد ميسيPLInwazja rozdymki na Morzu ŚródziemnymARتخبط إسرائيلي بعد ظهور السيسي بالزي العسكري.. خبير يتحدث لـRT عن صداع في تل أبيبCN台南全面追查問題油品,市長黃偉哲要求涉案產品全下架CN資深媒體人矢板明夫演講後遇襲,檢方認定涉境外勢力指使聲押被告ARمونديال 2026: الأرجنتين تواجه مصر وسويسرا تواجه كولومبيا في مواجهات حاسمةINTLIndia News Roundup: Landslide in Kerala, Soldier Ambush in Manipur, Missile Deal with IndonesiaDEJosef Hecken: "Ich habe mich oft unbeliebt gemacht"RUЛавров: Россия рассчитывает на участие главы комиссии Афросоюза в саммите Россия-АфрикаCRYPTO-FRMichael Saylor : Le Bitcoin doit-il rester figé pour prospérer ?ARمصر تواجه الأرجنتين في ثمن نهائي كأس العالم: صلاح ضد ميسيPLInwazja rozdymki na Morzu ŚródziemnymARتخبط إسرائيلي بعد ظهور السيسي بالزي العسكري.. خبير يتحدث لـRT عن صداع في تل أبيب
Newsgather
BackCoal India commissions solar power plant in Gujarat
NOTICIA
Economic Times05.05.2026Business1 dk okumaIndia

Coal India commissions solar power plant in Gujarat

Por qué importa

Coal India Limited, a state-owned company and a major domestic coal producer, is expanding its renewable energy portfolio as part of its strategy to become a Net Zero energy entity. This development follows criticism from the CAG regarding delays in solar project development.

Tamaño de fuente

State-owned Coal India Limited has commissioned a 100 MW solar power project in Gujarat. This marks a significant step in the company's renewable energy expansion. The project received its commissioning certificate from Gujarat Energy Development Agency. This development comes as Coal India aims to increase its solar capacity. The company is working towards becoming a Net Zero energy entity.

New Delhi: State-owned CIL on Tuesday announced the operationalisation of a 100 MW solar power project in Gujarat, marking a milestone in its renewable energy push.

In a filing to the BSE, Coal India Ltd (CIL) said, "it has received the commissioning certificate...from Gujarat Energy Development Agency (GEDA) for 100 MW capacity Solar Power Plant (in) Gujarat w.e.f. 31.03.2026."

CIL, a Maharatna PSU under the coal ministry, has been ramping up its renewable energy portfolio.

Coal India accounts for over 80 per cent of domestic coal production.

Government auditor CAG had in December pulled up Coal India Ltd for delays in development of the targeted 3,000 MW solar power projects, stating that the coal behemoth and its arms had installed only 122.492 MW of solar capacity by December 2024, which is just 4.08 per cent of the target.

Live Events

The Comptroller and Auditor General of India (CAG) had also asked Coal India to execute the projects on a fast-track basis to become a Net Zero energy company.

Preguntas abiertas

  • What is the total planned solar capacity for Coal India and the timeline for achieving it?
  • What are the specific challenges that led to past delays in solar project development?
  • How will this solar capacity contribute to Coal India's overall Net Zero targets?

Temas relacionados

This article was originally published by Economic Times.

Noticias relacionadas