DERND muss nach Podcast-Folge Fehler korrigierenESHallan muerta a una mujer y a su hija en una vivienda incendiada en Mijas (Málaga)CN賴清德針對中聯油食安事件提出4點原則 呼籲修食安法DEIran-Krieg: USA und Iran einigen sich auf WaffenruheCN新光三越擊敗微風廣場,取得台北車站商場經營權TRMason Greenwood'un Geleceği Belirsiz: Fenerbahçe ve Roma YarışıyorCN新北失業勞工子女生活補助受理申請 最高可獲3萬5800元RUГенсек НАТО: Россия остается долгосрочной угрозой для альянсаARأسعار الذهب تتأرجح وسط مخاوف التضخم وتوقعات رفع الفائدةRUБерега Антальи завалены мусором, туристы и местные жители возмущеныDERND muss nach Podcast-Folge Fehler korrigierenESHallan muerta a una mujer y a su hija en una vivienda incendiada en Mijas (Málaga)CN賴清德針對中聯油食安事件提出4點原則 呼籲修食安法DEIran-Krieg: USA und Iran einigen sich auf WaffenruheCN新光三越擊敗微風廣場,取得台北車站商場經營權TRMason Greenwood'un Geleceği Belirsiz: Fenerbahçe ve Roma YarışıyorCN新北失業勞工子女生活補助受理申請 最高可獲3萬5800元RUГенсек НАТО: Россия остается долгосрочной угрозой для альянсаARأسعار الذهب تتأرجح وسط مخاوف التضخم وتوقعات رفع الفائدةRUБерега Антальи завалены мусором, туристы и местные жители возмущены
Newsgather
BackHS2 Rail Line Review Points to Speed and Politics as Causes of Failure
HS2 Rail Line Review Points to Speed and Politics as Causes of Failure
En desarrollo
BBC News17.05.2026Transportation2 dk okuma

HS2 Rail Line Review Points to Speed and Politics as Causes of Failure

En resumen

  • A review of the HS2 rail line is expected to attribute its failures partly to a focus on maximum speeds and political pressure.
  • The report, by Sir Stephen Lovegrove, will likely echo previous findings about "original sins" like changing priorities and ballooning costs, and suggests lowering top speeds to save money.

Resumen generado por IA

Por qué importa

The High Speed 2 (HS2) project is a planned high-speed railway line in the United Kingdom. It has faced significant criticism regarding its cost, timeline, and scope since its inception. Recent decisions have seen parts of the original route cancelled.

Tamaño de fuente

The HS2 rail line failed in part due to a focus on achieving the highest possible speeds and political pressure, a review is expected to find.

The scheme has been undergoing a "reset", and in March Transport Secretary Heidi Alexander asked HS2 bosses to look at lowering top speeds to save money.

This latest report into HS2, expected to be published this week, is authored by former National Security Adviser Sir Stephen Lovegrove and has considered the implications for the civil service and public sector.

Its findings are expected to agree with a previous review that HS2's so-called "original sins" included changing political priorities and ballooning costs.

The review is also expected to highlight the "gold-plating" of the high-speed concept, "resulting in [a] bespoke and highly engineered design".

In the coming days, Alexander is expected to confirm that trains won't start running by the current target date of 2033 and will also provide an updated price tag for the project.

HS2's main purpose was to increase capacity on the rail network but it has suffered rising costs and delays.

Under the initial plans, first confirmed in 2012, the rail line would have run from London to Birmingham, and then on two separate lines to Leeds and Manchester.

However, in 2021, the government said it was cancelling the eastern leg going to Leeds. Two years later, the section between Manchester and Birmingham was also ditched.

In June 2025, Alexander said that after "a litany of failure" she was "drawing a line in the sand" and the government would get HS2 delivered.

Mark Wild, chief executive of the project's delivery company HS2 Ltd, was tasked with carrying out comprehensive "reset".

Earlier this year the transport secretary said she was "determined to explore every opportunity" to "bring down costs and delivery timetables" including reducing the top speeds of trains on the line.

HS2 had been designed to allow trains to run up to 360 km/h (224 mph), which would have made the line faster than any other conventional railway in the world.

Most high-speed trains in the UK run at around 220 km/h, while HS1, the Channel Tunnel Rail Link, reaches speeds of up to 300 km/h.

Although it will be years before the railway opens, HS2 is in its peak construction phase.

A number of key structures have been completed, for example the 10-mile tunnel under the Chilterns, and the Colne Valley viaduct.

As part of efforts to get the project back on track, HS2 Ltd has previously said it would slow or pause work such as the line towards Handsacre, so it could focus spend on areas which had fallen behind; notably the central section across Buckinghamshire, Oxfordshire and Northamptonshire.

Qué observar

Perspectiva de IA — posibilidades, no hechos

  • Transport Secretary will confirm delays to HS2 beyond 2033 and provide an updated price tag.

    Muy probable · En días

  • HS2 project will see further scope reductions or cost-saving measures implemented.

    Probable · En meses

Preguntas abiertas

  • What will be the final cost of the revised HS2 project?
  • What is the new projected completion date for the operational sections of HS2?
  • Will lowering the top speed significantly impact the project's ability to increase rail capacity?
  • What are the specific recommendations from Sir Stephen Lovegrove's review regarding civil service and public sector implications?

Temas relacionados

This article was originally published by BBC News.