ARالبحرين والكويت تطلقان صفارات الإنذار تحسباً لهجوم إيراني وشيكKR집중호우로 동대구역 경부선 열차 운행 차질DEHalbzeitshow beim WM-Finale: Justin Bieber bestätigtARترامب يربط قرار سحب القوات الأمريكية من أوروبا بمسألة غرينلاند وإيرانKR호르무즈 인근 남부 공습 이어 북부 지역까지BRVereador Abraão Sampaio Feitosa Kaxinawá é preso em flagrante em JordãoKR반도체 소부장 기업 주가, 레이저쎌 필두로 강세…코스닥 반등 시도INThai Authorities Investigate Drowning Death of Fitness Influencer Connor MurphyKR박정민 대표 "더 잘 연결해야…수익성 동반한 본질적 성장 하겠다"KR네이버 D2SF, 가상 엔터테인먼트 스타트업 '23세기아이들'에 신규 투자ARالبحرين والكويت تطلقان صفارات الإنذار تحسباً لهجوم إيراني وشيكKR집중호우로 동대구역 경부선 열차 운행 차질DEHalbzeitshow beim WM-Finale: Justin Bieber bestätigtARترامب يربط قرار سحب القوات الأمريكية من أوروبا بمسألة غرينلاند وإيرانKR호르무즈 인근 남부 공습 이어 북부 지역까지BRVereador Abraão Sampaio Feitosa Kaxinawá é preso em flagrante em JordãoKR반도체 소부장 기업 주가, 레이저쎌 필두로 강세…코스닥 반등 시도INThai Authorities Investigate Drowning Death of Fitness Influencer Connor MurphyKR박정민 대표 "더 잘 연결해야…수익성 동반한 본질적 성장 하겠다"KR네이버 D2SF, 가상 엔터테인먼트 스타트업 '23세기아이들'에 신규 투자
Newsgather
BackIndia invokes force majeure for West Asia conflict, allows 2-4 month contract extensions without penalties
India invokes force majeure for West Asia conflict, allows 2-4 month contract extensions without penalties
En développement
Times of India01.05.2026Business1 dk okumaIndia

India invokes force majeure for West Asia conflict, allows 2-4 month contract extensions without penalties

Finance ministry says conflict should be treated as 'war' to invoke clause; defence, drone, fertiliser and chemical sectors to get relief

L'essentiel

  • The finance ministry has said the West Asia conflict should be treated as a 'war' to invoke the force majeure clause in public contracts, allowing 2-4 month extensions without penalties.
  • The department of expenditure issued an office memorandum enabling relief for companies whose contractual obligations were affected by supply chain disruptions from Feb 27 onwards.
  • Sectors including defence, drone manufacturing, fertiliser and chemicals will benefit.

Résumé généré par IA

Pourquoi c'est important

The force majeure clause in Indian public contracts allows relief in extraordinary circumstances beyond human control, such as war. It frees parties from contractual liability and obligation when invoked properly.

Taille de police

The clause allows relief in extraordinary circumstances beyond human control, such as war, and frees parties from contractual liability NEW DELHI: The West Asia conflict should be treated as a "war" to invoke the 'force majeure' clause in public contracts where obligations have been impacted by disruptions, the finance ministry has said. It has allowed govt entities to extend contractual timelines by two to four months, without penalties, in cases where supply chain disruptions have affected execution. Industry executives said this would be a major relief for companies and contractors in sectors like defence, drone manufacturing, fertiliser and chemicals. The office memorandum issued by the department of expenditure says, "In cases where disruptions arising from the prevailing West Asia situation have directly affected or consequentially impacted contractual obligations (for goods and services contracts, construction/works contracts with govt agencies), the procuring entities may invoke 'force majeure'." The clause allows relief in extraordinary circumstances beyond human control, such as war, and once invoked, it "frees parties from contractual liability and obligation". The ministry specified that relief can be provided only in cases where companies or contractors had to complete obligations on or after Feb 27. The invocation of 'force majeure' would be considered valid only where parties were not in default as on Feb 27, it said. The department said the clause wouldn't absolve the non-performances that were not directly attributable to the West Asia situation. The period of extension will be given on a case-by-case basis by the procuring entity. Welcoming the decision, the president of Drone Federation India, Smit Shah, said on X, "Many Indian drone companies have govt contracts, and because of the ongoing conflict in West Asia, their supplies and deliveries have been badly affected. They were worried about heavy penalties for delays that were not even their fault... (The govt decision) gives relief to our member companies and sends a strong message that govt stands with the Indian industry during difficult times."

Questions ouvertes

  • How many contracts will be affected by this decision
  • Whether private sector contracts will also get similar relief
  • How the government will verify that delays were directly attributable to the West Asia situation