FRCoupe du Monde 2026 : l'Argentine renverse l'Égypte (3-2) et se qualifie pour les quarts de finaleFRMarine Le Pen annonce sa candidature à la présidentielle après la réduction de sa peine d'inéligibilitéRUОдин беспилотник сбит на подлете к ЧереповцуKR인천 옹진군 호우주의보 발효FRAffaire des assistants parlementaires du FN : Marine Le Pen condamnée en appel, mais peut-elle encore se présenter en 2027 ?RUИсточник: Теракт в Дамаске мог быть провокацией ГУР УкраиныTRNATO'nun 2026 Savunma Harcaması Tahminleri: Toplam 1.8 Trilyon DolarUSDragonfly Dogfights Mirror Human Fighter Pilot Tactics, Study FindsVNViên chức quản lý có thể bị xem xét cho từ chức nếu người thân vi phạm pháp luậtESBegoña Gómez, ausente en la cumbre de la OTAN en Ankara por orden judicialFRCoupe du Monde 2026 : l'Argentine renverse l'Égypte (3-2) et se qualifie pour les quarts de finaleFRMarine Le Pen annonce sa candidature à la présidentielle après la réduction de sa peine d'inéligibilitéRUОдин беспилотник сбит на подлете к ЧереповцуKR인천 옹진군 호우주의보 발효FRAffaire des assistants parlementaires du FN : Marine Le Pen condamnée en appel, mais peut-elle encore se présenter en 2027 ?RUИсточник: Теракт в Дамаске мог быть провокацией ГУР УкраиныTRNATO'nun 2026 Savunma Harcaması Tahminleri: Toplam 1.8 Trilyon DolarUSDragonfly Dogfights Mirror Human Fighter Pilot Tactics, Study FindsVNViên chức quản lý có thể bị xem xét cho từ chức nếu người thân vi phạm pháp luậtESBegoña Gómez, ausente en la cumbre de la OTAN en Ankara por orden judicial
Newsgather
GeriMarinus Link Viability Questioned Amidst Tasmania's AI Data Centre Expansion
Gelişiyor
ABC Top Stories17.06.2026Energy3 dk okumaAustralia

Marinus Link Viability Questioned Amidst Tasmania's AI Data Centre Expansion

Hızlı Bakış

  • Energy industry voices are questioning the viability of the Marinus Link project due to the rapid expansion of AI data centres in Tasmania.
  • These data centres require significant energy, potentially consuming a large portion of the state's supply, which could impact the project's business case.

Yapay zekâ özeti

Neden Önemli?

The Marinus Link is a proposed undersea cable to transfer energy between Tasmania and Victoria. Its viability is being questioned due to the growing energy demands of AI data centres in Tasmania.

Yazı boyutu

Energy industry voices are warning that the business case for Marinus Link appears increasingly unviable if power-hungry players such as AI data centres continue to expand across Tasmania.

Firmus Technologies, a Singapore-based company led by co-founders Oliver Curtis and Tim Rosenfield, has designs on using a significant portion of Tasmania's energy to power three AI data centres in the state's north.

It has already locked in more than 100 megawatts for its St Leonards precinct, which is currently under construction.

Two more Firmus centres are planned: one in Bell Bay, north of Launceston; and another in Wesley Vale, in the state's north-west. The power requirements across the three sites are estimated to be 400 megawatts, or about two-fifths of the state's total power supplies if more generation is not added.

Those high energy needs were enough for the boss of a federal agency charged with advising the government on climate policy to express some doubt towards another energy infrastructure project — Marinus Link.

"Just look at Tasmania, for example," Climate Council Authority chair Matt Kean said during a Q&A at the Morgan Stanley Australia Summit in Sydney last week.

"It's an evolving market," Mr Kean would go on to tell the global investment bank's summit, which is held over several days and plays host to business leaders, investors and analysts.

"Government policy needs to keep up with those rapid shifts if we're to realise the opportunity."

Firmus declined to provide comment for this story.

'You can't do both', energy expert says

The $5 billion Marinus Link is a proposed 1,500-megawatt two-way undersea data cable between Heybridge in Tasmania's north-west and the Latrobe Valley in Victoria.

Jointly funded by the state and federal governments, the development will allow energy to be sent between the states, and on into the National Electricity Market (NEM).

The project promises to allow Tasmania to import low-cost renewable energy, while it reserves and stores its hydropower, which can then be exported to the mainland when required.

In February, the Australian Economic Regulator green-lit the first stage of the project.

Loading...

Hydro Tasmania's claim that the undersea Bass Strait cable Marinus Link will make the state an extra $450 million in profit a year was "now looking quite questionable" according to an energy analyst.

The Tasmanian government remains firmly committed to the project, but energy analyst Marc White of Goanna Energy, says he believes energy commitments made to data centres in Tasmania have weakened the project's business case.

"Effectively you've got a limited capacity to trade, and if you're making decisions to use that capacity to firm up renewables in Tassie, then that's capacity that you don't have to trade on the market.

"If that energy has to be allocated to local businesses, then you can't do both."

A Marinus Link spokesperson said the increased investment in data centres is further proof of the necessity of the project, which will enable new investment in renewable generation and major load infrastructure.

"Importantly for Tasmania, Marinus Link will enable hydropower assets to operate more strategically — storing energy when renewable supply is abundant and dispatching it whenever it is needed most," the spokesperson said.

Power bill hike possible, report finds

Tasmania's cool climate and access to renewable energy has made it an attractive place for AI data centre investment, even while some of its major industrial energy users face an uncertain future.

Aside from Firmus's proposals, Australian mining company Greenwing is also investigating the potential for data centre expansion in Tasmania.

Greenwing hopes to reopen the mothballed Que River Mine, about 75 kilometres south of Burnie in Tasmania's north-west, but said its longer-term plan was to assess whether the site can host third-party data infrastructure, such as data centres or artificial intelligence (AI) infrastructure.

Data centres have rapidly spread across Australia, with 162 in operation and more than 90 in the pipeline, according to recent Climate Council research.

Grid-scale batteries across the NEM are also expanding rapidly, which, according to the Australian Energy Market Operator (AEMO), make up just under half of the total capacity in the NEM pipeline.

A new report, by the Victorian Energy Policy Centre for the Bob Brown Foundation, has found the rollout of affordable and efficient batteries has blunted Tasmania's competitive advantage in cheaper energy storage, further eroding the business case for Marinus Link.

The report predicted an electricity bill hike for Tasmanians, in the form of increased network charges, if Marinus Link went ahead.

It also found the state only had a small exportable surplus of energy beyond its current capacity.

It said only a "catastrophic contraction of demand", such as the closure of major industrials Liberty Bell Bay and Nyrstar, would make it viable to expand data centre development in the state.

Bundan Sonra Ne Olabilir?

Yapay zekâ öngörüsü — kesinlik taşımaz

  • Marinus Link project faces significant hurdles or potential cancellation.

    Muhtemel · Aylar içinde

Açık Sorular

  • Can Tasmania's energy generation meet both data centre and Marinus Link needs?
  • What will be the final decision on Marinus Link's future?
  • How will government policy adapt to these energy shifts?