Australia's Snowy 2.0 Project Nears Completion Amidst Cost Overruns and Safety Concerns
Auf einen Blick
- Australia's Snowy 2.0 energy project, the nation's most expensive, has seen tunnelling machines pierce a key rock stretch, advancing its completion.
- However, the project faces significant cost blowouts, safety issues, and delays, with its final price tag expected to be much higher than the initial $2 billion estimate.
KI-generierte Zusammenfassung
Warum es wichtig ist
Snowy 2.0 is an expansion of Australia's original Snowy Mountains hydro-electric scheme, designed to act as a giant battery for excess renewable energy. Announced in 2017, it aims to connect two reservoirs via a 27-kilometre underground tunnel system.
Deep under the Snowy Mountains, tunnelling machines have pierced through a key stretch of rock, edging Australia's most expensive energy project one step closer to completion.
The way is now cleared for work to begin on the Snowy 2.0 power station itself.
But questions remain about whether it will ever justify its cost.
The project in the NSW Kosciuszko National Park is seven years behind schedule, and its initial budget of $2 billion looks quaint in hindsight.
Based on Snowy Hydro's most recent costings of $12 billion, the project has blown out by around $3 million a day.
The government-owned energy company has admitted the final price tag will be much higher.
Snowy 2.0 has also faced scrutiny over ongoing safety issues and the revelation that executives collected more than $1.2 million in bonuses despite missing financial targets.
In May, Snowy Hydro chief executive Dennis Barnes acknowledged the project's difficulties but stood by its importance.
"Like most mega-projects in Australia and globally, Snowy 2.0's cost has increased; Snowy 2.0's scale and uniqueness have compounded the increase," he said.
Australia's most ambitious energy project
Snowy 2.0 was announced in 2017 by former prime minister Malcolm Turnbull.
It is an expansion of the Snowy Mountains hydro-electric scheme that was completed in 1974 at a cost of $820 million. Adjusting for inflation, that figure would be more than $8.5 billion today.
The project will connect two existing reservoirs at Tantangara and Talbingo via a 27-kilometre underground tunnel system and act like a giant battery.
Excess wind and solar energy will be used to power reversible turbines that will pump water from Talbingo via a hydro-electric power station 800 metres underground to the higher-elevation reservoir at Tantangara.
When demand surges, water will then be released back down the hill, generating electricity.
Upon completion, the pumped hydro power station will produce 2.2 gigawatts of power at full capacity, which Snowy Hydro claims is enough to power 3 million homes for a week.
Blowouts and sinkholes
Just months after the project was announced, a feasibility study revealed costs had more than doubled to $4.5 billion.
In 2018, the federal government bought the New South Wales and Victorian governments' stakes in Snowy Hydro Limited for $6 billion, so when early works began in 2019, it was entirely Commonwealth-owned.
In April that year, Perth-based construction company Clough and its Italian joint venture partner, Salini Impregilo, were awarded the major works contract valued $5.1 billion.
They would go on to form Future Generation Joint Venture (FGJV), which would be responsible for the project's construction.
The Black Summer bushfires and COVID-19 caused unexpected delays less than a year into construction.
From 2021, three tunnel boring machines (TBMs) were deployed to carve out the tunnel network.
The first two TBMs, named Lady Eileen Hudson and Kirsten, completed the main access and emergency escape and ventilation tunnels with few issues.
But the third machine, Florence, had troubles from the start.
In February 2023, Florence became stuck after hitting soft ground just 150 metres into the excavation of a 15-kilometre tunnel linking Tantangara Reservoir to the underground power station site at Lobs Hole.
The ground above collapsed, creating a sinkhole, and Florence was stuck for roughly 11 months.
During this time, there were also leadership troubles, with chief executive and managing director of Snowy Hydro Paul Broad resigning in June 2022.
At the end of the year, Clough had collapsed and its Australian business was bought out by Salini Impregilo, which had rebranded to WeBuild.
Despite these setbacks, the project received a glowing review from the Australian National Audit Office (ANAO) in 2022.
It stated that Snowy Hydro's governance of the early implementation of the project was "effective" and the report had no recommendations.
At that time, the project was on track to be finished by 2026–27.
Budget reset
In August 2023, the project's budget was reset, increasing to $12 billion, or six times the original estimate.
Meanwhile, the completion date was extended to 2028.
Snowy Hydro said the construction proceeded despite the project's design being "immature" and more "expensive and complex than anticipated".
Investigations by ABC's Four Corners revealed that the setbacks caused by Florence alone may have cost the project $2 billion.
The ABC also brought safety concerns into the spotlight, including a toxic gas leak in July 2023 followed by a tunnel collapse in 2024.
Rising costs, delays, and safety issues continued into 2025.
A ventilation fan imploded in February, in May workers went on strike over pay, and in July SafeWork NSW closed a concrete testing lab due to silica exposure concerns.
By then, Snowy Hydro was waiting on the arrival of the fourth tunnel boring machine it had purchased to help complete the project.
In October 2025, Snowy Hydro confirmed it would require additional funding to complete the project, citing rising supply chain costs, productivity challenges, and expensive new tunnelling equipment.
A month prior, Snowy Hydro's chief executive, Dennis Barnes, was paid a $323,000 bonus as part of more than $1 million in executive bonuses for the project meeting its targets.
These targets included customer satisfaction, safety, and work culture, and the bonuses were awarded despite missing financial targets.
This year, reports of safety issues have continued.
Snowy Hydro recently confirmed two incidents, one from January 2025, where a truck was close to falling off a cliff, and another in January this year, where a worker was hit by an excavator boom.
Snowy Hydro said the contractors involved in the incidents had made changes in consultation with SafeWork NSW.
Is it worth it?
Budget papers show the government is expediting funding to the project, with $2.9 billion in loan funds earmarked for 2026–27, double the amount planned in the previous budget, as costs continue to escalate.
Those costs are currently being scrutinised in a fresh review, the results of which are expected to be independently verified and should be released in the coming months.
Meanwhile, a new ANAO audit is expected to be delivered this month, looking at whether Snowy 2.0 is being managed in a way that delivers value for money.
The question of whether the project will ultimately justify its price tag has divided experts.
Andrew Blakers, an engineering professor at the Australian National University, said the potential of Snowy 2.0 could not be overstated.
"[It] is absolutely world-class in terms of the amount of energy storage," he said.
But former energy executive Ted Woodley argued the project would come up against physical limitations.
"If and when the upper reservoir is empty, it has to be refilled," he said.
Mr Woodley argued that pumping water back uphill could only occur when electricity prices were low enough to justify the cost, meaning recharging could take "weeks or months".
"Theoretically, yes, it can produce for a week, but in practical terms it probably never will," he said.
Meanwhile, Mr Woodley believed the project was not accounting for all expenses, including infrastructure like transmission lines and inflation, which, if included, would realise a final cost of $42 billion.
He said the rapid improvement in battery technology meant the project was "not economic" at that price.
"There's been a dramatic and unbelievable development in battery technology that I think very few people saw," he said.
Professor Blakers agreed that batteries should be part of our renewable future and that they complement pumped hydro.
"If you want big-scale storage, you go for pumped hydro. If you want high-power short-term storage, you go for batteries," he said.
"But if you want a robust energy system, you go for both batteries and pumped hydro."
Last week, the demolition of the Liddell coal-fired power station provided a powerful image of the energy transition well and truly underway.
Professor Blakers said Snowy 2.0 coming online would help to lower prices by competing with fossil fuel generation.
"Coal and gas do very well every night-time when there's no wind and sunshine, meaning prices go up because coal and gas don't have competition," he said.
Professor Blakers said ultimately the hefty investment in the project would be worth it.
"Once it's built, it costs almost nothing to run for the next 100 or 200 years," he said.
"If you have a bad week where it is wet and windy over much of the south-east, then Snowy 2.0 will come into its own."
Snowy 2.0's power station is expected to start generating power in late 2027 and is slated for completion in December 2028.
Worauf zu achten ist
KI-Ausblick — Möglichkeiten, keine Fakten
The project will face further scrutiny regarding its value for money.
Sehr wahrscheinlich · Innerhalb von Monaten
The final cost will exceed the current $12 billion estimate.
Wahrscheinlich · Mittelfristig
Snowy 2.0 will commence generating power by late 2027.
Möglich · Mittelfristig
Offene Fragen
- Will the final cost justify the project's benefits?
- What are the specific findings of the latest cost review and ANAO audit?
- How will the project's operational costs compare to battery storage in the long term?
- What further safety measures will be implemented to prevent future incidents?

