ITDaniel Siad, presunto reclutatore di Jeffrey Epstein, trovato morto vicino a ParigiBRInstagram fora do ar? Rede social apresenta instabilidade nesta quarta-feiraITBorse europee in rialzo, trainate dai titoli energeticiUKEngland Amputee Football Team Struggles for World Cup Funding Despite Nations League WinESEstados Unidos busca desmantelar el Tribunal Penal Internacional, según Marco RubioDESPD unterstützt Thorsten Frei als möglichen UnionsfraktionschefCN腱鞘巨细胞瘤专病门诊在北京大学人民医院开诊KR국조특위 국힘 의원들 "국조·특검 함께 해야 국민 불신 풀릴 것"RUUkrainian Attacks Target Civilians on Russian Black Sea Coast, Says State Duma DeputyITBilancio delle vittime del doppio terremoto in Venezuela sale a 5.346ITDaniel Siad, presunto reclutatore di Jeffrey Epstein, trovato morto vicino a ParigiBRInstagram fora do ar? Rede social apresenta instabilidade nesta quarta-feiraITBorse europee in rialzo, trainate dai titoli energeticiUKEngland Amputee Football Team Struggles for World Cup Funding Despite Nations League WinESEstados Unidos busca desmantelar el Tribunal Penal Internacional, según Marco RubioDESPD unterstützt Thorsten Frei als möglichen UnionsfraktionschefCN腱鞘巨细胞瘤专病门诊在北京大学人民医院开诊KR국조특위 국힘 의원들 "국조·특검 함께 해야 국민 불신 풀릴 것"RUUkrainian Attacks Target Civilians on Russian Black Sea Coast, Says State Duma DeputyITBilancio delle vittime del doppio terremoto in Venezuela sale a 5.346
Newsgather
RetourSizewell C nuclear plant cost faces 'significant uncertainty', watchdog warns
Sizewell C nuclear plant cost faces 'significant uncertainty', watchdog warns
En développement
Guardian UK19/05/2026Energy3 min de lectureUnited Kingdom

Sizewell C nuclear plant cost faces 'significant uncertainty', watchdog warns

L'essentiel

  • The UK's spending watchdog, the NAO, warns Sizewell C nuclear plant's £38bn cost faces "significant uncertainty" and may not benefit households until 2064.
  • Risks are substantial and borne by the public, despite government claims of future savings.

Résumé généré par IA

Taille de police

The cost of the government’s £38bn nuclear plant in Suffolk is subject to “significant uncertainty” and may outweigh the benefits for UK households until at least 2064, according to the government’s spending watchdog.

The National Audit Office (NAO) has warned that although the potential benefits of the Sizewell C nuclear plant are considerable, they remain uncertain. The risks, however, are “immediate, substantial and borne by the public”.

The government claims the nuclear reactor, expected to generate the equivalent of enough low-carbon electricity to power 6m homes when it begins operations in the late 2030s, could save £2bn a year from the electricity system compared with using other low-carbon technologies.

However, for households the overall savings could be outstripped by the cost of supporting its construction until almost halfway through its 60-year operational life. The project could take even longer to “break even” if there are cost overruns or delays, the NAO warned.

“Sizewell C is a project of exceptional scale, complexity and significance for taxpayers,” said Sir Geoffrey Clifton-Brown, the chair of the public accounts committee, which oversees the work of the NAO. “Experience from comparable nuclear projects in the UK and overseas highlights their vulnerability to delays and cost overruns.”

Sizewell C is being developed by French state nuclear company EDF as a successor project to the Hinkley Point C reactor in Somerset, the first nuclear plant to be built in the UK in a decade. It has invested £1.1bn to take a 12.5% stake in the project alongside the UK government, which has invested £14.2bn as the majority stakeholder.

British Gas’s parent company, Centrica, owns 15% of Sizewell C while the Canadian pension fund La Caisse and the investment fund Amber Infrastructure own 20% and 7.6%, respectively.

Nigel Cann, the chief executive of Sizewell C, said the cost on household bills were an “investment in lower long-term electricity costs” which will “deliver value to consumers and to the country for the rest of this century”.

The project is already adding value to the UK by creating thousands of jobs and boosting businesses across the country, Cann added. Sizewell C said it had so far come good on its promise to source 70% of its construction value from UK suppliers and had spent just under £5bn.

“All major infrastructure projects involve uncertainty, and the report highlights the steps we’re taking to reduce risk and control costs,” Cann said.

A government spokesperson said investing in large-scale nuclear power was the “only way to get our country off the rollercoaster of volatile global gas markets”.

Households began paying for the Sizewell C project via home energy bills at the start of the year to help fund construction. This financial framework, known as a regulated asset base model, is a marked change from the Hinkley Point deal, which will begin to earn a guaranteed stream of revenues from home energy bills only once it begins generating in the early 2030s.

Critics of the regulated asset base model, including the campaign group Stop Sizewell C, have warned that any construction delays could mean that bill payers support Sizewell without receiving power for longer than expected, while the government would be on the hook for the project’s financial risk.

Stop Sizewell C said the risks surrounding the project “could easily turn Sizewell C into a financial disaster” while the funding model meant its investors were “the only ones who can’t lose”.

The NAO has urged the government to mitigate the risk by using “close monitoring, greater transparency to parliament, and by securing value for money from the significant public and private investment”.

Sujets liés

This article was originally published by Guardian UK.

Articles liés

Jackdaw gas field emissions 'won't materially influence global warming', says owner
En développement·08/07/2026

Jackdaw gas field emissions 'won't materially influence global warming', says owner

Adura's updated Environmental Impact Assessment states emissions from the controversial Jackdaw gas field will account for less than 0.02% of annual global greenhouse gases, asserting they "not materially influence" global warming. This report was mandated by regulators after a previous submission was deemed inadequate and following a legal challenge from environmental groups.

BBC UK News
1 min de lecture
Plus sur ce sujetsizewell c