Breaking
ARحريق هائل في إسبانيا يخلف عشرات القتلى والجرحى وسط مخاوف من تفاقم الوضعGLOBALAnn Widdecombe murder investigation launched, manhunt underwayRUПосольство РФ: вандализму на советском кладбище в Нидерландах нет оправданияCRYPTO-ENHong Kong Crypto Platforms Must Ditch OTPs for Logins by July 2027RUБританский политик: Заявление Лаврова подчеркивает раскол между Россией и ЗападомUSDisney+ Considers Free Content Tier to Boost CompetitionGLOBALCNBC Investing Club: Nasdaq Slips, Intel Falls, Earnings AheadPLUE proponuje inteligentne ograniczniki prędkości w samochodachINTLSteam Machine Verification System Now Live, Hidden in Steam Deck DetailsFRSaisie de 2,5 tonnes de cannabis au Havre, une prise recordARحريق هائل في إسبانيا يخلف عشرات القتلى والجرحى وسط مخاوف من تفاقم الوضعGLOBALAnn Widdecombe murder investigation launched, manhunt underwayRUПосольство РФ: вандализму на советском кладбище в Нидерландах нет оправданияCRYPTO-ENHong Kong Crypto Platforms Must Ditch OTPs for Logins by July 2027RUБританский политик: Заявление Лаврова подчеркивает раскол между Россией и ЗападомUSDisney+ Considers Free Content Tier to Boost CompetitionGLOBALCNBC Investing Club: Nasdaq Slips, Intel Falls, Earnings AheadPLUE proponuje inteligentne ograniczniki prędkości w samochodachINTLSteam Machine Verification System Now Live, Hidden in Steam Deck DetailsFRSaisie de 2,5 tonnes de cannabis au Havre, une prise record
Newsgather
BackTransmission Bottlenecks Threaten India's Renewable Energy Goals
Transmission Bottlenecks Threaten India's Renewable Energy Goals
Developing
Economic Times4/20/2026Business2 min readIndia

Transmission Bottlenecks Threaten India's Renewable Energy Goals

PGCIL controls 84% of inter-regional transmission but faces 6-24 month delays on key projects amid ₹3 lakh crore capex programme

Quick Look

  • India's renewable energy ambitions face headwinds as Power Grid Corporation of India Ltd struggles with transmission project delays of 6-24 months due to land acquisition and forest clearance issues.
  • The company controls 84% of India's inter-regional transmission capacity but execution lags are eroding profitability, with ROE falling from 18.5% in FY23 to 15.3% in FY26, while its ₹3 lakh crore capex programme strains operational capacity.

AI-generated summary

Why It Matters

India aims to achieve 500 GW of renewable energy capacity by 2030. PGCIL, as the dominant transmission utility, is critical to this goal but faces execution challenges on its massive infrastructure expansion programme.

Font size

India's ambitious push toward renewable energy is facing growing strain from transmission bottlenecks and execution challenges, a report by proxy firm InGovern Research Services said. The report highlights Power Grid Corporation of India Ltd's (PGCIL) dominant position in the sector, noting that the company controls nearly 84% of India's inter-regional transmission capacity and secured over half of the competitive project awards in FY25.

"PGCIL's timely execution benefits shareholders, but transmission lags behind RE generation commissioning," the report said, adding that Central Transmission Utility of India Ltd's (CTUIL) September 2025 data shows PGCIL executing the majority of the 50 ongoing ISTS-TBCB schemes (e.g., Khavda-II, Koppal-II-Raichur), many were delayed by 6-24 months.

The report attributes these delays largely to land acquisition challenges, right-of-way disputes, and forest clearance issues. While such hurdles are common across infrastructure projects, the report notes that their impact is magnified by PGCIL's large and concentrated project load. At the same time, PGCIL is undertaking an aggressive capital expenditure programme of ₹3 lakh crore through FY32, including ₹32,000 crore planned for FY26 alone. With an existing project pipeline worth ₹1.48 lakh crore, the scale is stretching operational capacity and raising concerns about timely delivery.

Execution delays are beginning to weigh on financial performance. PGCIL's return on net worth has declined from 18.5% in FY23 to around 15.3% in the first nine months of FY26. Under the tariff-based competitive bidding framework, projects generate returns only after commissioning-meaning delays directly erode profitability. A one-year delay, the report estimates, can reduce the equity internal rate of return by about 200 basis points.

Meanwhile, capital tied up in unfinished projects has surged. Capital work-in-progress stands at approximately ₹1.2 lakh crore, while the company's debt-to-equity ratio has risen to around 1.45x, indicating increasing leverage and pressure on capital efficiency.

Transmission delays are also impacting renewable energy output. Despite stable annual profits of ₹15,000-16,000 crore, PGCIL's stock performance has lagged. The company delivered a roughly 12% CAGR between FY20 and FY26, compared to 18% for the Nifty 50. Analysts suggest markets are factoring in execution risks and concerns over capital deployment.

Dividend payouts have also declined-from ₹14.75 per share in FY22 to ₹9.00 per share in FY25-as the company retains more earnings to fund its capex programme with no corresponding increase in commissioned assets.

Open Questions

  • How will PGCIL address land acquisition bottlenecks?
  • What specific measures is the company taking to accelerate project execution?
  • Will the government provide additional support or policy interventions?

Related Topics

This article was originally published by Economic Times.

Related Stories