Rosseti is implementing an investment program in the Yaroslavl region aimed at modernizing and developing the electrical grid infrastructure, including the construction of new substations and road lighting.
The Rosseti company, with the support of the government of the Yaroslavl region, is beginning the construction of a new electrical substation in the Kuznechikhinsky settlement, and plans also include a project to illuminate the route from Yaroslavl to Uglich, said Governor Mikhail Evraev.
“We are starting to build a new substation with Rosseti in the Kuznechikha settlement. It will provide electricity to the Zavolzhsky district of Yaroslavl, the territory of the Yaroslavl district, including Kuznechikha,” Evraev said during the direct line.
The company also plans a project to illuminate the highway from Yaroslavl to Uglich. The work is expected to last two years and is planned to begin this year, the governor noted. Preparations for the project will begin in September.
According to Evraev, in 2026, the volume of investments made by Rosseti in the implementation of projects in the Yaroslavl region amounted to more than 4 billion rubles. The investment program has been drawn up until 2030 and is designed for 14 billion rubles. The program plans, in particular, the reconstruction and construction of more than 1 thousand kilometers of networks, the construction of the Kuznechikha substation and the modernization of two substations in Pereslavl-Zalessky.
AI outlook — possibilities, not facts
Work on lighting the route from Yaroslavl to Uglich will begin this year
Very likely · Within months
The volume of Rosseti investments in the Yaroslavl region will grow within the framework of the program until 2030
Likely · Within years

Gazprom states that Europe's underground gas storage facilities are only 67.3% full as of September 8, 12.8 billion cubic meters below last year's level, with gas prices reaching late 2022 crisis highs of over $1,000 per 1,000 cubic meters, narrowing the window for replenishment before the heating season and increasing supply reliability risks for European consumers.

Governor of the Kaliningrad region Alexey Besprozvannykh announced that gasification of Baltiysk will be completed by September 1, 2027. The first stage has already been completed and covered about 5 thousand residents, the second stage will be completed by March 2027 for another 7 thousand people, the third stage - for the remaining 4 thousand residents by the beginning of the 2027 heating season.

High gas prices and a backlog in filling underground gas storage facilities increase the risks to Europe's reliable gas supply during the cold period, Gazprom reported on September 10 in Moscow.

Gas prices in Europe have reached levels typical of the December 2022 energy crisis, exceeding $1,000 per 1,000 cubic meters at major hubs with day-ahead delivery, Gazprom said.

The approach of the heating season in Europe is reducing the ability to restore gas reserves in underground storage facilities, leaving the market vulnerable to rising demand, import disruptions and competition with Asia for liquefied natural gas, Gazprom said.

Analysts of the Telegram channel “Hard Figures” and Dmitry Polevoy from “Astra Asset Management” believe that the reduction of the Central Bank key rate by 0.25 percentage points. September 11 may be a manifestation of regulator optimism, despite continued high inflation and growth in the money supply. Most experts expect the rate to remain at 14%, but some, including Goldman Sachs, predict a decrease to 13.75%. The decision will be announced on Friday at 1:30 p.m.