Alrosa brought the Svetlinskaya HPP to its design capacity of 370 MW
Investments in the project exceeded 5 billion rubles
Quick Look
- The Alrosa company commissioned the fourth hydroelectric unit of the Svetlinskaya HPP in Yakutia, reaching a design capacity of 370 MW.
- The facility, built on permafrost, provides energy for the industrial and social needs of the Western Energy Region.
AI-generated summary
Why It Matters
The Svetlinskaya HPP is the world's first hydroelectric power station built on permafrost. The station provides electricity to Alrosa's industrial facilities and the Western Energy District of Yakutia.
MOSCOW, September 16 - RIA Novosti. Alrosa has brought the Svetlinskaya HPP to its design capacity of 370 MW, investments in the project exceeded 5 billion rubles, the company’s press service reported.
Alrosa is putting into operation the fourth hydroelectric unit of the Svetlinskaya hydroelectric power station (Vilyuiskaya HPP-3). With its launch, the station reached its designed installed capacity of 370 MW... Investments in the project exceeded 5 billion rubles,” the statement says.
The launch ceremony was attended by Deputy Prime Minister of the Russian Federation - Presidential Plenipotentiary Representative in the Far Eastern Federal District Yuri Trutnev, Head of Yakutia Aisen Nikolaev and General Director of Alrosa Pavel Marinychev.
It is noted that this is the world’s first hydroelectric power station built on permafrost, and not on the rocky foundation traditional for such objects. It refers to experimental hydraulic structures.
“The hydroelectric power station provides electricity to Alrosa’s production facilities and works in the interests of the entire Western energy region of Yakutia. Among its consumers are enterprises of the oil and gas and gold mining industries, as well as objects of transport, telecommunications and social infrastructure,” the message clarifies.
According to the release, the equipment was entirely manufactured in Russia by the leading manufacturer of hydropower equipment, Power Machines.
Installation of the main equipment began in December. In August, the hydraulic unit was installed and tested. It will be put into operation more than six months earlier than the project deadline - April 2027, the company emphasized.
Alrosa provides 76% of its electricity needs from renewable sources, according to the company’s report.
Open Questions
- The impact of early launch on the overall return on investment of the project.