Three days of pressure and leakage tests were successfully carried out at the Akkuyu NPP, built by the Russian State Nuclear Energy Corporation Rosatom.
AI-generated summary
The construction and testing processes of the Akkuyu Nuclear Power Plant, built by the Russian State Nuclear Energy Corporation Rosatom, are continuing gradually.
In the power plant built by the Russian State Nuclear Energy Corporation Rosatom, four steam generators, steam armature blocks and feed water pipelines were checked during three-day tests.
THE TEMPERATURE REACHED 135 DEGREES
Steam generators and their associated pipelines were tested under a pressure of 12.6 megapascals (MPa). While the steam generators were heated to 126 degrees before the test, the temperature of the water reached 135 degrees during the tests.
While the pressure was gradually increased, the operating parameters of the equipment and the tightness of the connection points were checked. The system was kept at maximum pressure for a certain period of time, and then the pressure was reduced to 10.1 MPa and final examinations were made.
Following the checks, the pressure resistance of the second circuit equipment and its suitability for the next test stages were confirmed. It was reported that the test results enabled the start of preparations for hot tests of the reactor facility at the 1st power unit.
STATEMENT FROM AUTHORIZED NAME
Akkuyu Nükleer AŞ General Manager Sergei Butckikh, whose views were included in the statement, stated that the tests confirmed the durability of the second circuit equipment and the quality of the assembly and welded connections and added:
"This result is the result of extensive joint work carried out by construction teams, installation and commissioning experts, operating personnel, as well as representatives of external expert organizations of Rosatom, which carried out direct technical supervision during the tests. The results obtained allow us to start preparations for hot tests of the reactor plant at power unit 1."
In addition to Akkuyu Nükleer AŞ Technical Directorate personnel, Rosatom's electrical energy division Atomtechenergo and Rosatom Servis AŞ technical inspection experts and representatives of the Nuclear Regulatory Authority took part in the tests.
AI outlook — possibilities, not facts
Hot tests of the reactor plant will start at the 1st power unit
Very likely · Within weeks

Minister of Energy and Natural Resources Alparslan Bayraktar stated that Türkiye was not affected by supply crises thanks to its energy diversification strategy. The Minister shared the 2040 vision, the 1 million barrel oil production target and the latest situation at the Akkuyu Nuclear Power Plant.

Minister of Energy Bayraktar emphasized Türkiye's domestic resource, diversification and nuclear energy strategies against global energy crises. Sharing TPAO's production targets and the latest situation in Akkuyu NPP, the Minister stated that they will highlight the electrification-focused action plan at COP31.
Minister of Energy and Natural Resources Alparslan Bayraktar announced that electrification will be at the center of the National Energy 2040 Vision, which will be announced on November 5. Evaluating TPAO's production targets and the latest situation in Akkuyu NPP, Bayraktar stated that energy supports will continue.
Russian Deputy Prime Minister Novak stated that Russia's diesel shipments are continuing and that they are ready to supply natural gas if Europe requests. Novak emphasized that Russia has alternative markets and stated that the gas sales problem belongs to Europe.
Minister of Energy and Natural Resources Bayraktar announced at the Turkey Energy Summit that nuclear power plant negotiations with Russia, South Korea and China are continuing, that Oruç Reis will go to Pakistan and that they are interested in Lebanon projects.

Barış Erdeniz, President of the Electricity Distribution Services Association, stated that they foresee an investment need of at least 50 billion dollars in the electricity distribution infrastructure in Türkiye in the next 10 years, and that they target 22 billion dollars in the next 5 years.