Bitcoin miner seeks definitive lease for 32-megawatt Big Boden facility, contingent on financing and upgrades
AI-generated summary
HIVE Digital Technologies is transitioning from Bitcoin mining to AI infrastructure, having already signed a three-year AI computing agreement with Bell Canada and Cohere covering 2,304 Nvidia GPUs. The company reports $185 million in contracted GPU-cloud annualized run-rate revenue, with $40 million currently live.
Bitcoin miner HIVE Digital Technologies is eyeing $45 million in annual revenue from an AI data center in Sweden, but it still hasn't secured a final lease.
In its latest earnings update, HIVE reiterated that its 32-megawatt Big Boden facility could generate the sum through a long-term colocation arrangement. That revenue depends on a definitive agreement, financing, facility upgrades, and the project entering service.
The company first disclosed the proposal in June. It involves an unnamed, investment-grade Swedish technology company and contemplates a lease lasting up to 10 years. During Tuesday's earnings call, CEO Aydin Kilic said the parties were negotiating deposits, termination rights, and other terms that could affect financing costs. A lender's consultant had visited the site the previous week, he said.
“We do not want to rush into a deal just for the sake of reporting new top-line revenue,” Kilic said, according to the earnings call transcript.
HIVE expects to seek financing for the Boden project after securing a signed lease, potentially through corporate bonds. The company has not announced a completion date for negotiations.
From crypto mining to AI infrastructure
The existing data center would also need a substantial makeover. HIVE plans to retrofit it for up to 10,000 Nvidia GB300 GPUs, using liquid cooling to handle high-density computing racks.
Although the facility has a 32-megawatt utility connection, the proposed customer would receive approximately 25 megawatts of usable computing capacity, with the remaining power supporting data center operations.
“This site has evolved from a GPU compute facility supporting Ethereum,” Kilic said when announcing the letter of intent, describing its planned conversion into a more powerful AI installation.
The expansion follows HIVE's broader effort to move beyond Bitcoin mining, a shift that has already produced several large GPU-cloud contracts.
HIVE signed a major three-year AI computing agreement with Bell Canada and Cohere in June, covering 2,304 Nvidia GPUs as it expanded beyond crypto mining.
HIVE now reports $185 million in contracted GPU-cloud annualized run-rate revenue, although only $40 million is live. The remainder represents contracted capacity that has not yet entered service.
The company is targeting approximately $700 million in total high-performance computing annualized revenue by the end of 2028, though that figure includes projects requiring additional financing, construction, and customer commitments.
For Boden, HIVE's next milestone is securing a definitive lease before proceeding with project financing.
AI outlook — possibilities, not facts
HIVE will secure a definitive lease for the Big Boden facility
Possible · Within weeks
HIVE will seek financing for the Boden project after securing a signed lease, potentially through corporate bonds
Possible · Within months

Bitcoin's proposal repository added three draft specifications (BIP458, BIP459, BIP460) between Nov. 2-4 that introduce signature aggregation to lower fees for jointly assembled payments and input consolidation, with half-aggregation reducing signature payloads by 45% and full aggregation by 90%.

Crosschain bridging protocol Across warned users Tuesday not to access its app or connect wallets while investigating a potential security incident, as users reported losses including $9,000 in USDC and 7,053 USDT0. Separately, NEAR AI disclosed a Monday breach exploiting an SGLang vulnerability that exposed data from approximately 100 users and 18 AI agents.

Near AI disclosed a breach exposing account information for about 100 users and data from 18 AI agents after an attacker exploited a remote code execution vulnerability in SGLang software running on its servers. The company revoked credentials, rotated tokens, and notified affected users.

Google DeepMind reports two AI agents reproduced a known 1024-bit RSA digital signature computation over nearly four days with about 20 human messages, achieving about a 3.5-fold reduction in CPU use compared with an earlier team's work, without recovering a private key.

Elon Musk endorsed Anthropic's Claude Opus 5.5 as a masterpiece and admitted Grok 4.8 will not be as good, while predicting Grok 5 could exceed Opus 5.5 in two or three months. Grok 4.8 has finished pretraining and is undergoing reinforcement learning, with a limited rollout to Bot users expected later this week.

A November 4 preprint by Thomas Mosk finds software-flaw disclosures at firms with early access to Anthropic's Claude Mythos Preview rose roughly 120% relative to Chinese firms without access, with no detectable slowdown in repair times. The study covers October 2025 through September 2026 and cautions that selection into Anthropic's Project Glasswing was not random.