The 6.59-km-long tunnel breakthrough connects two excavated sections, marking a significant milestone in the 125-km Himalayan rail project.
Indian Railways completed a breakthrough in the 6.59-km Tunnel-14 of the 125-km Rishikesh-Karnaprayag railway project in Uttarakhand's Rudraprayag district, overcoming complex Himalayan terrain and geological challenges.
AI-generated summary
The 125-km Rishikesh-Karnaprayag rail line is an infrastructure initiative involving extensive tunnelling and bridge construction through the Himalayas.
Indian Railways has achieved a major construction milestone in the 125-km Rishikesh-Karnaprayag railway project in Uttarakhand, completing the breakthrough in the 6.59-km-long Tunnel-14 in Rudraprayag district.
The breakthrough connects two excavated sections of the tunnel, bringing the ambitious Himalayan rail project closer to completion.
The tunnel connects a 4.7-km stretch excavated from Portal-1 at Sumerpur with a 1.79-km section from Portal-2 at Marora.
The achievement marks an important step in the construction of the railway line, which is expected to improve connectivity across Uttarakhand and make travel to key pilgrimage destinations easier.
The construction of Tunnel-14 involved several engineering challenges due to the region's complex geological conditions.
A 110-metre triple-track section near Portal-1 passes through loose soil beneath inhabited areas, with an overburden of just 20-30 metres.
Engineers used pre-excavation and multi-drifting techniques to carry out the excavation safely.
At Portal-2, the slope was stabilised using 30-35-metre micropiles, 15-20-metre rock bolts and consolidation grouting.
The main excavation drive began in March 2024, after ground settlement at Marora and issues concerning land and house acquisition were resolved.
Around 100 metres of excavation at Portal-2 was completed mechanically.
Controlled blasting was restricted to daytime near the tunnel portals to minimise risks to nearby settlements.
Ventilation systems were also installed throughout the 4.7-km drive from Portal-1.
The 125-km Rishikesh-Karnaprayag railway project is among Indian Railways' most challenging infrastructure initiatives, involving extensive tunnelling and bridge construction through the Himalayan terrain.
Union Railway Minister Ashwini Vaishnaw highlighted the project's progress on October 22, describing it as a major engineering achievement.
Taking to social media platform X, Vaishnaw said, “Engineering through the Himalayas! 125 km, 12 stations, 83% tunnels. The Rishikesh-Karnaprayag rail line is not just a track; it's Uttarakhand's lifeline to the future.”
The project features 16 tunnels and 19 bridges, reflecting the scale of engineering work required to build a railway network through the mountainous region.
The railway line is expected to improve access to several important towns and pilgrimage destinations, including Karnaprayag and Rudraprayag.
It is also expected to provide a boost to tourism and regional economic development.
Highlighting its importance for pilgrims and national security, Vaishnaw said, “Once this project is completed, travel to Karnaprayag, Rudraprayag, and pilgrimages to Kedarnath and Badrinath will become vastly easier.”
He also pointed to the railway line's strategic significance, noting that its terminal station at Karnaprayag is located just 123 km from the India-China border.
The project is expected to strengthen transport infrastructure in Uttarakhand while improving connectivity to remote Himalayan areas.
Its completion could also make travel for residents, tourists and pilgrims more convenient.
A U.S. Trade Representative report examining excess capacity in Indian manufacturing inadvertently validates the success of initiatives like Make in India, highlighting massive growth in exports such as smartphones, telecom equipment, and pharmaceuticals to the United States.
Bisleri International disputed FSSAI findings of coliform bacteria in a West Bengal water sample, citing independent lab tests that showed compliance. The company recalled the batch while urging a review, amid broader FSSAI surveillance.
A group of current and former Microsoft workers published an open letter using CEO Satya Nadella's words to demand a say in AI development, as the company faces backlash over flat wages and offers historic buyouts to 60,000 employees.
Karnataka Deputy CM DK Shivakumar plans to implement Japanese urban development and waste management models in the state. The initiative aims to boost infrastructure, attract foreign investment, and create 600 technical jobs via Kawasaki Heavy Industries.
The ITAT Chennai granted partial relief to a salaried insurance employee who deposited Rs 1.17 crore in cash from a side coconut business, deleting an unexplained money addition and directing a taxed business income estimate instead.
The century-old Thornbury Picture House at 802 High Street, Thornbury, Melbourne, will be auctioned on December 3 with a price guide of $2.5 million to $2.75 million, marking its first sale in 46 years. The property includes a 57-seat independent cinema leased until 2028 and a three-bedroom upstairs residence.