Temporary transmission towers to restore power while permanent replacements may take a year
AI-generated summary
Storm activity last week downed two transmission towers and severely damaged a third on a farm at Wharminda along a 270-kilometre transmission line between Port Lincoln and Cultana. More than 20,000 properties on the Eyre Peninsula and West Coast lost power on Thursday.
The southern Eyre Peninsula is expected to be reconnected to the national electricity grid by Friday morning, after storm activity last week downed two transmission towers and severely damaged a third.
More than 20,000 properties on the peninsula and West Coast lost power on Thursday during the severe weather, and while construction has begun on temporary towers, operators say it could take a year for permanent structures to be installed.
The damaged towers were located on a farm at Wharminda, which sits along a 270-kilometre transmission line between Port Lincoln and Cultana.
Electricity transmission operator ElectraNet said local generation restored power for Port Lincoln and surrounding areas on Thursday night, and the network had to be reconfigured to allow services to return to some other parts of the Eyre Peninsula.
Following their installation, the four temporary towers would need to be tested before being re-energised, which would restore transmission services from Cultana to Port Lincoln.
ElectraNet chief executive Simon Emms said he was hoping services would be operational by early Friday.
“We're actually going to put up temporary towers each side of the existing line route, and then route the existing conductors around that,” he said.
SA Power Networks had advised residents in and around Port Lincoln of a planned power outage occurring on Thursday night while the region is reconnected to the transmission network.
Mr Emms said the temporary towers have been built to the same standard as the current line.
ElectraNet confident in tower design
Mr Emms said on Wednesday the three transmission towers were damaged by a “localised, very severe wind event”, and he was confident they had been built to the right strength.
“We know the towers are designed to the appropriate Australian standard. That design has been checked, independently checked, and we also built a test tower and tested it to destruction,” he said.
Mr Emms said ElectraNet would undertake a “thorough and complete” investigation into the incident.
Following the storms last week, ElectraNet had suggested the towers were likely brought down by a “one-in-2,000-year weather event”, something the SA government said would form part of investigations into the incident.
Mr Emms said new permanent transmission towers would need to be built in place of the three damaged structures, which he estimated could take up to a year.
“One of the longest lead times is actually getting all of the right steel together to build that,” he said.
ElectraNet executive Alex Trento said Port Lincoln residents would need to continue to leave their rooftop solar inverters off until told otherwise, to prevent the generator coming offline before the transmission line had been restored.
AI outlook — possibilities, not facts
Transmission services from Cultana to Port Lincoln will be restored by early Friday morning.
Likely · Within hours
Permanent replacement transmission towers will take up to a year to build.
Likely · Within months
The South Australian government will critically examine ElectraNet's claim that a one-in-2,000-year weather event caused the Eyre Peninsula blackout, which left over 20,000 properties without power after two transmission towers collapsed and a third was damaged during intense storms.

Victoria's electricity supply is at risk as the Yallourn coal plant, supplying a fifth of the state's energy, shuts in 2028. Experts warn neither Labor nor the Coalition has a viable plan to fill the shortfall, with rising demand from datacentres and electrification compounding the challenge.
About 24,000 properties on South Australia's Eyre Peninsula were left without power after a storm damaged three transmission towers, crippling the radial line serving Port Lincoln. Residents are counting on temporary fixes from the mothballed Port Lincoln power station and reconfigured lines to last weeks while permanent tower replacements are planned.
ElectraNet faces scrutiny after a rare weather event damaged three transmission towers on South Australia's Eyre Peninsula, causing a blackout just three years after a $300 million network upgrade promised more reliable power.
Experts warn Victoria could face blackouts within two years as the Yallourn coal plant closes in 2028, with the Coalition's gas plan deemed unachievable for at least five years. The state's energy transition relies on transmission projects facing community backlash and cost blowouts, while gas reserves deplete and new exploration would take years to yield generation.
Storms brought down multiple electricity transmission towers on South Australia's Eyre Peninsula, leaving more than 24,000 properties without power. ElectraNet is working to restore supply, while SA's cabinet emergency management committee will meet at 7pm tonight.