海鯤號為中華民國海軍自製潛艦,原定今年底交付,但因技術問題延誤近一年,海軍曾處以罰款。前海軍顧問郭璽長期關注國艦國造進程,曾公開批評各項系統整合不良。
潛艦海鯤號的交艦期限愈來愈近。(資料照)
〔記者洪定宏/高雄報導〕雖然潛艦海鯤號持續海測、調校,但距離台船承諾的今年底之前交艦期限只剩約2.5個月,且因延誤交艦近1年,被海軍罰款數千萬元。前海軍顧問郭璽認為,IPMS(整合式儎台管理系統)不更換,海測一定出問題;針對郭璽的評論,台船均不回應。
郭璽10月8日在YT頻道節目以「海鯤號交艦堪憂」為題指出,海測就是要將所有系統整合到IPMS,但連結過程,各項問題逐漸出現,例如魚雷管竟還要手動才能發射,戰情中心也無法指揮,導致外界質疑6根魚雷管僅用操雷測試2根,沒有全部測試。
請繼續往下閱讀...
郭璽表示,海鯤號更換IPMS只需花一兩千萬,但台船不換、持續花冤枉錢,賠光固定盈餘;尤其負責救難的大武艦也用同一家公司的IPMS,依舊出問題,海鯤號更複雜,不更換,系統怎麼連結?
據了解,海鯤號只剩最後階段的跨夜耐航與深度潛航測試等幾個科目,原本外界預期10月5日開始,將每週出海測試,但10月2日海測後,持續停靠碼頭調校。
AI outlook — possibilities, not facts
海軍將在交艦期限前要求台船解決IPMS系統問題或面臨額外罰款
Likely · Within weeks

Faced with the expansion of Russian and Chinese nuclear weapons, the U.S. Navy awarded five prototype research and development agreements with a total value of US$744 million through the Strategic Systems Program Office to promote the nuclear-armed sea-launched cruise missile (SLCM-N) project. It is expected to be integrated into Virginia-class submarines, enter the system development stage in 2028, and be fully mass-produced in 2034. However, it will occupy the space of traditional Tomahawk missiles and increase the burden of nuclear weapons.

The USS Lincoln returned to its home port of San Diego, California on October 8 after more than 300 days of deployment at sea, ending a record of 265 consecutive days without docking. During the deployment, there were reports that life on the ship deteriorated, and at least eight service members attempted suicide, raising concerns about the impact of long deployments on the mental health of service members.

U.S. Defense Secretary Pete Hegseth said the public will be able to watch a live broadcast of Nadal Malik Hassan's execution by firing squad in what would be the first public execution in the U.S. in nearly a century. Hassan was sentenced to death for shooting 13 unarmed U.S. soldiers at the Fort Hood military base in Texas in 2009. His execution date is set for December 3. Although Trump has approved the decision, legal experts have questioned its legality, noting that Hassan's appeal process has not yet concluded and that the live broadcast of the execution may face platform policy restrictions and ethical disputes.

The U.S. Navy plans to award Raytheon a single-source contract to initiate low-rate initial mass production of the Joint Multiple Effects Warhead System (JMEWS) and integrate the warhead into the Tomahawk Block Vb missile to enhance its ability to strike hard targets such as underground bunkers and missile sites. The cooperation is based on Raytheon's long-term status as the sole supplier of Tomahawk missiles. Other manufacturers can still submit capability statements before October 22.

The USS Lincoln aircraft carrier returned to San Diego after 321 days of deployment. The outer wall of the ship island displayed 103 drones and 34 ship kill marks. Secretary of War Hegseth boarded the ship to check the markings, but the numbers were different from the official results of 77 drones and 64 ships announced by the US military. The reason has not yet been explained.

Taiwan's first two F-16V Block 70 fighter jets arrived at Taitung's Zhihang Base on October 2. Strategy expert Liao Hongxiang pointed out that Taiwan's air force base has four major weaknesses: short geographical warning time, weak ground defense forces, insufficient physical bunker capacity, and traditional machine fortress protection blind spots. If the protection is not upgraded simultaneously, it may become the enemy's precision attack target. He suggested six specific actions, including establishing a layered protection system, strengthening machine fort protection, and expanding the monitoring scope.