中广核浙江三澳核电项目4号机组于11月10日正式开工。该项目位于浙江温州,采用“华龙一号”技术,是长三角首个引入民营资本参股的核电项目,建成后预计年发电量达90亿千瓦时。
AI-generated summary
三澳核电项目规划建设6台“华龙一号”机组,是长三角地区首个此类项目,也是中国首个引入民营资本参股的核电项目。
中新社北京11月10日电 (记者 庞无忌)记者10日从中国广核集团获悉,当日,中广核浙江三澳核电项目4号机组主体工程正式开工。
三澳核电项目地处浙江省温州市,是长江三角洲地区首个“华龙一号”项目,也是中国首个引入民营资本参股的核电项目。本次开工的4号机组属于三澳核电项目二期工程,是中广核今年正式开工的第3台核电机组。该机组于2024年8月19日获国家核准,采用中国拥有完全自主知识产权的“华龙一号”三代核电技术,建成后预计年发电量可达90亿千瓦时,可满足约100万人口的年生产生活用电需求。
中广核苍南核电有限公司董事长杜延辉表示,现场团队在保证安全质量的前提下,持续通过工艺迭代优化、智能工装升级、微小改进等多项举措,保障施工节点按计划高质量推进。项目建设以来,已应用预制可拆卸挡墙、预埋件热镦技术等多项先进技术,后续将应用模块化施工、自动焊接等先进建造技术。
据悉,三澳核电项目规划建设6台“华龙一号”机组,分三期建设,目前已核准4台。其中,1号机组已正式投产发电,2号机组已完成首次核燃料装载,3号机组正在开展核岛周边厂房主体结构施工,整体建设按计划稳步推进。6台机组全部建成后,年发电能力预计超540亿千瓦时,接近温州市当前全社会年用电总量的80%,每年可等效减少标准煤消耗超1635万吨、减排二氧化碳近5000万吨。
作为长三角南翼重要清洁能源基地,三澳核电项目有望为长三角绿色低碳转型以及算力枢纽、智能经济高质量发展提供保障。

The concrete pouring of the first tank of the nuclear island of Unit 4 of CGN Zhejiang Sanao Nuclear Power Project has started, marking the official start of the main project and the second phase of the project entering full construction. The unit uses the "Hualong One" third-generation nuclear power technology. After completion, it is expected to generate 9 billion kilowatt-hours of electricity annually, which can meet the electricity needs of about 1 million people.

As of November 10, Zhejiang's inter-provincial spot electricity purchases in 2026 reached 10.427 billion kilowatt hours, accounting for 24% of the national transaction volume. Zhejiang uses an artificial intelligence-assisted decision-making system to cope with fluctuations in new energy sources and peak power balance pressures within the province through mutual aid between provinces, and has purchased more than 10 billion in electricity for three consecutive years.

Indonesia is partnering with China to expand solar power and energy storage, but a new Celios report warns of a multibillion-dollar funding gap and demands for greater domestic control.

Qinghai Province issued the "Fifteenth Five-Year Plan for CSP Development in Qinghai Province", which clearly focuses on CSP + high-temperature heat storage to solve the pain points of new energy "rich summers and dry winters, and daily gains and losses". It is proposed that by 2030, the total installed capacity of CSP under construction and operation will reach 8 million kilowatts, and it will make every effort to build "China's CSP Capital".

The construction of solar panels on industrial land next to the Butai Fishing Market in Chiayi County triggered a backlash from residents, who were worried about the heat island effect and reflection. The energy company held a second briefing meeting today. Because residents questioned that the minutes of the first meeting did not truthfully record their objections and started construction without communication, the two sides were in a stalemate and the briefing ended unhappily.

Affected by the cold air, Northeast my country and other regions are facing a peak period of energy supply guarantee. Shanxi, Inner Mongolia, Xinjiang and other coal production bases have increased production. Inner Mongolia's Shendong coal output exceeded 16 million tons in October. Shanxi's average daily output increased by 6.4% compared with August. Xinjiang's coal export trains reached 80 per day. Coal storage in unified power plants across the country is available for 35 days.