Court decision highlights problems in crisis management, network maintenance and delay in restoring power after cyclone
AI-generated summary
Enel faced a large-scale blackout following an extratropical cyclone in December 2025. ANEEL carried out technical supervision over the company's performance during the event.
Tree falls on Avenida Fábio Prado, in Chácara Klabin, and hits a car. — Photo: Personal archive
The São Paulo Court recognized flaws in the provision of energy supply services by Enel during the blackout caused by the extratropical cyclone that hit the capital and the metropolitan region on December 9th and 10th, 2025. The decision highlights problems in managing the crisis, mobilizing teams and maintaining the electrical network.
The decision was handed down by judge Gisele Valle Monteiro da Rocha last Friday (4), in a public civil action filed by the Public Defender's Office and the Public Ministry. Enel was also ordered to pay procedural costs and expenses. There is still an appeal.
The judge rejected the concessionaire's argument that the weather phenomenon, in itself, would be enough to eliminate its responsibility.
According to the decision, although the cyclone caused the interruptions, it was not the exclusive cause of the extent of the damage or the delay in restoring the energy supply.
For the judge, storms, windstorms and cyclones are part of the predictable risks of energy distribution activities, especially in a metropolitan region subject to severe weather events. Therefore, the concessionaire must maintain infrastructure, planning and operational capacity to prevent and reduce impacts on the population.
When contacted, Enel did not respond until the last update of this report.
Flaws highlighted
The decision considered, among other elements, Technical Note No. 9/2026-SFT/ANEEL, produced as a result of inspections of the company's performance during the blackout.
The document identified problems in crisis management, in the mobilization of teams, in the availability of vehicles and equipment, in the contingency plan and in preventive maintenance of the network.
Among the flaws highlighted are:
concentration of teams during business hours;
significant reduction in personnel during the night and early morning;
insufficient use of large vehicles;
employment of teams without specific preparation for complex occurrences;
low resolution of services;
deficiencies in the control of vegetation close to the network.
The strong wind that hits São Paulo knocked Santa Claus off the Christmas decorations on Avenida Paulista — Photo: Reanto S. Cerqueira/ Ato Press/Estadão Conteúdo
More than 3 thousand incidents took more than 24 hours to be resolved
According to data from the technical note reproduced in the ruling, the network recorded 6,715 occurrences of supply interruptions on December 10.
Of this total, 3,056 incidents (46%) took more than 24 hours to be resolved. Together, they reached 759,304 consumer units.
The number of 6,715 corresponds to records of network interruptions, and not the number of people or properties affected. Each incident could affect several consumers.
According to the decision, there were consumers who were left without power until the sixth day after the weather event. The longest recorded outage lasted 142.8 hours, the equivalent of almost six days.
For Justice, the data shows that the intensity of the cyclone may explain the beginning of the interruptions, but does not justify the excessive delay in restoring the service.
The ruling states that the losses were aggravated by insufficient planning, maintenance and response capacity on the part of the concessionaire.
AI outlook — possibilities, not facts
Enel will appeal the court decision.
Very likely · Within weeks

O ministro Luiz Fux, do STF, concedeu uma prorrogação de 15 dias ao contrato entre o BRB e o TJ-BA. A medida visa permitir que a Caixa Econômica Federal se manifeste sobre alegações do banco, facilitando negociações de federalização.

A juíza Raíssa da Silva Santos Amaral suspendeu as regras que permitiam a reeleição na Câmara Municipal de Cáceres, após ação do vereador Professor Domingos. A decisão exige que a eleição de dezembro siga a redação anterior da Lei Orgânica municipal.

A Justiça do Maranhão ordenou que o Rio Poty Hotel, em São Luís, demula construções irregulares em áreas públicas no prazo de dois anos. A decisão aponta ocupação indevida de vias e calçadas, além de falha na fiscalização pela Prefeitura municipal.

O Tribunal de Justiça do Maranhão iniciou processo administrativo para rescindir contrato com o Banco de Brasília devido a falhas operacionais e atrasos na liberação de depósitos judiciais, precatórios e RPVs ao longo de 2026.
O Ministério da Justiça do Brasil removeu ou bloqueou 86.176 sites e perfis que divulgavam apostas online ilegais. A operação, realizada em conjunto com o Ministério da Fazenda, impactou cerca de 74,7 milhões de usuários em diversas redes sociais.

A Justiça do Rio Grande do Norte suspendeu as obras da nova Cadeia Pública de Alcaçuz, em Nísia Floresta, devido a irregularidades no licenciamento ambiental e ausência de estudos técnicos exigidos por lei.