BRFM Sergipe does 'Pre-Caju Heat' on Orla da AtalaiaCNPGO Weili 150 ABS brand new gasoline-electric motorcycle is on the road. It has both level 1 fuel economy and a 37L large cabin. It is a high-cost transportation choice for commuters.CN"Freedom Day Shoot" commemorates Sun Yat-sen's mention of Taiwan and Xi repeats the old tune of "complete reunification of the motherland"USThe unfolding Jensen Huang scandal: a timelineCNAI Shock Bomb Huida Huang Renxun ResignsDEInsiders report Jensen Huang's third affair - again with an Nvidia employeeAULive: Cummins to address ball tampering claims after Khawaja revelationsITBeppe Fiorello and Achille Lauro light up the night of the ATP FinalsBRSara dos Santos wins gold in boxing at the Youth Olympic GamesITNvidia closes on the Nasdaq at -4.34%, over 400 billion burned since the beginning of the weekBRFM Sergipe does 'Pre-Caju Heat' on Orla da AtalaiaCNPGO Weili 150 ABS brand new gasoline-electric motorcycle is on the road. It has both level 1 fuel economy and a 37L large cabin. It is a high-cost transportation choice for commuters.CN"Freedom Day Shoot" commemorates Sun Yat-sen's mention of Taiwan and Xi repeats the old tune of "complete reunification of the motherland"USThe unfolding Jensen Huang scandal: a timelineCNAI Shock Bomb Huida Huang Renxun ResignsDEInsiders report Jensen Huang's third affair - again with an Nvidia employeeAULive: Cummins to address ball tampering claims after Khawaja revelationsITBeppe Fiorello and Achille Lauro light up the night of the ATP FinalsBRSara dos Santos wins gold in boxing at the Youth Olympic GamesITNvidia closes on the Nasdaq at -4.34%, over 400 billion burned since the beginning of the week
BackNebius tests the neocloud playbook with $40 billion in planned spending
Nebius tests the neocloud playbook with $40 billion in planned spending
Urgent
TechCrunch11 minutes agoBusiness3 min readUnited States

Nebius tests the neocloud playbook with $40 billion in planned spending

The neocloud company's ambitious buildout relies on customer prepayments and contract-backed loans as third-party site delays threaten its timeline.

Quick Look

  • Nebius announced $40 billion in planned 2027 spending, far above Wall Street expectations, relying on customer prepayments and contract-backed loans to finance data center construction.
  • The strategy faces risk from delays at third-party sites, including a Microsoft-backed Vineland, New Jersey facility months behind schedule.
  • Nebius cut its 2026 revenue forecast by $200 million to $3 billion, and shares fell 17%.

AI-generated summary

Why It Matters

Nebius is a neocloud company planning $40 billion in 2027 spending, financed largely through customer prepayments and loans backed by customer contracts. Its largest customer is Microsoft, which pays for AI computing capacity at a Vineland, New Jersey data center operated by DataOne. The site is months behind schedule due to generator issues and a transition to Bloom Energy fuel cells. DataOne faces a $1.1 million fine from New Jersey regulators and a noise-complaint lawsuit from residents.

Font size

In its third-quarter earnings call Thursday, the neocloud company Nebius laid out $40 billion in planned spending for 2027, far more than Wall Street had expected. It’s an ambitious plan, but it rests on a string of planned projects that are already starting to show cracks.

Nebius plans to fund the buildout by relying on customer pre-payments and loans backed by customer contracts — essentially using the future value of its data centers to finance their construction. But that can be a risky strategy if those projects get bogged down by delays or cancellations.

“Building at this scale is hard, and delays are part of our industry right now,” CEO Arkady Volozh said during Thursday’s earnings call. “We are not immune.”

The earnings announcement comes on the heels of reports that Microsoft is cooling on neocloud deals that aren’t delivering on time. That’s a problem for companies like Nebius, whose financing strategy is becoming more dependent on repayments. Because if it can’t get to capacity on time, it will keep piling on costs while revenues slip.

One of Nebius’s largest customers is Microsoft, which is paying for AI computing capacity at a Vineland, New Jersey data center that is now months behind schedule. Nebius’s contract with Microsoft is worth up to $19.4 billion, but it’s already letting deadlines slip. Only just over half of the Microsoft capacity is now planned for delivery by the end of the year, with the rest coming in Q2 2027.

The delay is because DataOne, the third party operator of the site, “decided to wind down the temporary generation faster than it was expected,” according to Andrey Korolenko, chief product and infrastructure officer, as the site switches over to Bloom Energy fuel cells.

Still, that transition wasn’t entirely by choice. In August, the investigative site Floodlight identified at least 45 natural gas generators in operation at the DataOne site, even though it had not received any permits for operating gas generators. New Jersey regulators fined the DataOne facility $1.1 million in response, finding that the use of the generators violated federal law.

DataOne is also facing a noise-complaint lawsuit from nearby residents over a constant humming noise allegedly emitted by the data center.

According to Nebius’s summary of its Microsoft contract, Microsoft can terminate affected service after a grace period if dates are missed and no alternative capacity is offered. The tranches were originally meant to be deployed in 2025 and 2026, so a Q2 2027 delivery date falls well beyond that window. The contract also includes financial penalties for late delivery.

Nebius said that Microsoft “has been part of the planning process.” Nebius did not say whether Microsoft has agreed to the new dates, but Microsoft has not publicly canceled anything.

TechCrunch has reached out to Nebius, Microsoft, and DataOne for comment.

On the call, Marc Boroditsky, Nebius’s chief revenue officer said the company’s deals with Microsoft and Meta both came with significant prepayment, which arrived long before delivery. But Bloomberg reported last week that Microsoft is tightening oversight on projects run by third parties, including Nebius, IREN, and Nscale, and debating whether it’s worth signing new agreements. Microsoft also sent employees to the site in New Jersey, per Bloomberg.

In its own quarterly earnings report, Microsoft noted that its capex spend was lower than expected due to third-party delays. The company is clearly not above pulling back from planned agreements where its partner doesn’t meet its share of the bargain. Bloomberg also reported that Microsoft won’t use an option to more than double its Nscale agreement for a Texas data center and recently stopped being an anchor customer for Nscale’s planned Essex site after power delays.

Nebius says the delays it faces are coming from sites it doesn’t control, with the data centers it is building itself coming online on time or ahead of schedule. Those, Nebius says, will supply most of its new capacity from 2027. New deals signed in Q3 came with prepayments that more than cover the cost of building capacity behind them, says Boroditsky. Nebius ended the quarter with $7.4 billion in cash.

Total prepayments plus asset-backed financing of investment-grade contracts are expected to cover up to 85% of the $40 to $45 billion 2027 capex spend. CFO Maria Del Dado Alonso Sanchez named Microsoft and Meta as contracts that can be financed this way. Boroditsky also said Nebius could “tap prepayments to shore up any additional cash requirements.”

Nebius forecast 2027 revenue of $12 to $13 billion, and said it expects to break even on a pre-tax basis by the fourth quarter.

Nebius reported third-quarter revenue of $981 million, up 571% from a year earlier. Roughly a third of that was a one-time payment tied to a new partnership model. Nebius cut its 2026 revenue forecast by $200 million to $3 billion, citing delays to third-party sites like New Jersey. Shares ended the day down 17%.

What to Watch

AI outlook — possibilities, not facts

  • Microsoft will continue to tighten oversight on third-party neocloud projects and may decline to sign new agreements.

    Likely · Within months

  • Nebius will face continued pressure on its 2027 capex timeline if third-party site delays persist.

    Likely · Within months

Open Questions

  • Has Microsoft agreed to the new delivery dates for the Vineland data center?
  • Will Microsoft cancel any Nebius contracts or pull back from planned agreements?
  • What is the status of Nebius's own data center builds that are reportedly on time or ahead of schedule?

Related Topics

This article was originally published by TechCrunch.

Related Stories

The unfolding Jensen Huang scandal: a timeline
BREAKING·

The unfolding Jensen Huang scandal: a timeline

Nvidia co-founder Jensen Huang resigned as CEO on November 11, 2026, after admitting to a 40-year marriage infidelity involving alleged Chinese spy Alice Huang and Nvidia executive Kimberly Powell. CFO Colette Kress was named interim CEO, Harvey C. Jones became board chair, and Huang agreed to testify before Congress before Thanksgiving as U.S. officials investigate national security implications tied to Nvidia chip exports to China.

TechCrunch
7 min read
Five ways Jensen Huang’s ouster from Nvidia could damage the AI industry
BREAKING·

Five ways Jensen Huang’s ouster from Nvidia could damage the AI industry

Nvidia's board ousted CEO Jensen Huang on Thursday after he confessed to an affair with a woman suspected by the U.S. government of being a Chinese spy and an executive at a Singapore-based neocloud suspected of smuggling Nvidia chips to China. The scandal threatens Huang's advocacy for open-weight AI, industry self-regulation, and Nvidia's data center financing strategy as the company enters a post-founder era.

TechCrunch
5 min read
More on this topicnebius