Energy North's proposed Project Ares in the Barkly Region faces strict environmental impact statement requirements.
The NT Environment Protection Authority has expressed a low level of confidence in the environmental planning for Energy North's proposed Project Ares data centre in the Barkly Region, requiring a comprehensive environmental impact statement.
AI-generated summary
Energy North applied to build a hyperscale data centre campus on Murranji cattle station, extracting up to 4 billion litres of groundwater annually.
The Northern Territory's environmental regulator says it holds a "low level of confidence" in the environmental planning behind a massive outback data centre.
Energy North has applied to build a hyperscale data centre campus on Murranji cattle station in the Barkly Region.
Called Project Ares, the facility would extract up to 4 billion litres of groundwater annually and require significant on-site power infrastructure.
The NT Environment Protection Authority said, if built, the data centre could have "a significant impact on the environment" and listed 10 potential impacts on air, water, people and land.
Responding to Energy North's environmental management plans in a publicly available document, the NT EPA said there was "insufficient information on most environmental aspects".
It said the regulator was not confident the environmental measures put forward by the company would be effective.
The application has not been rejected, and Energy North will now be required to submit more information in an environmental impact statement (EIS), and the NT EPA will consult further with the public and federal government.
Project Ares will also require assessment and approval from the national EPA before it can proceed.
The Albanese government is working on national data centre standards to be legislated in 2027 as it seeks to balance economic opportunities with environmental considerations.
The new laws could also include mandates to prioritise the use of recycled water and force AI companies to reserve computing capacity for Australian businesses and researchers.
In a separate statement published yesterday, the NT EPA acknowledged this and said the approvals process may be affected by the new laws.
"The Australian Government is developing policy expectations for data centres and AI infrastructure," it said.
"As policy and industry evolve, requirements of proponents and environmental impact assessment processes will also evolve," the statement read.
Environment Centre NT's Bree Ahrens welcomed the NT EPA's decision and said no development should take place until "robust" national laws are in place.
She said the regulator's decision to approach the proposal with "a really high level of scrutiny" was not surprising.
Energy North vice-president Daniel Hunter said the company agreed with the NT EPA's reasoning and said the project should be assessed thoroughly.
"One of the NT EPA's key concerns was that our measures to avoid and manage potential impacts weren't yet developed in detail," Mr Hunter said.
"That's a fair assessment, and it's exactly the gap the EIS is designed to fill, with management plans and specific, measurable commitments, backed by detailed technical studies."
He said Energy North proposed to be assessed via an EIS in its original application.
Mr Hunter said Project Ares would align with the federal government's proposed new laws.
"It will generate all its own power … so it won't draw on the existing electricity grid," he said.
"We know the community has real questions about water and gas. We'll be engaging with the community on those questions, and the EIS will address them in detail."
AI outlook — possibilities, not facts
Energy North will submit an environmental impact statement.
Very likely · Within months
Civil society organisations in Indonesia's West Kalimantan province have filed a class action lawsuit against the national government, alleging negligence in handling annual peatland fires and haze that have caused widespread respiratory illness, with plaintiffs demanding emergency declaration, health care, and prosecution of those responsible.
Tassal, a Canadian-owned salmon company, will begin individually injecting diseased fish with oxytetracycline in Tasmania's D'Entrecasteaux Channel this week, marking a new practice for the state. The move follows controversy over the industry's use of florfenicol last summer, which was later banned by the APVMA due to risks to non-target species. Tassal says it is awaiting approval to resume florfenicol use but is using OTC in the interim, claiming it allows for more targeted treatment with less medicine. Industry leaders emphasize animal welfare and resilience breeding, while environmentalists and wild fisheries raise concerns about antibiotic pollution and ecosystem impacts.
Western Australia will boost its shark mitigation budget by $5 million to expand shark tagging, increase aerial and drone surveillance, and investigate AI-powered shark-spotting drones following a fatal shark attack at Sorrento Beach and a whale carcass washing up at City Beach, which has also triggered E. coli-related beach closures.
Nepal has ended search and rescue operations for the August 26 flood that killed at least 1,455 people, with 5,285 still missing. Authorities are shifting to rehabilitation and legal processes to declare missing persons dead for insurance and banking purposes. Simultaneously, Nepal will begin a high-stakes project to drain four high-altitude glacial lakes—Thulagi, Lower Barun, Lumding Tsho, and Hongu II—to reduce future flood risks, a process that could take up to six years and includes sensor installation, flood forecasting, and community resilience efforts.
Danggu Geikie Gorge National Park in Western Australia's Kimberley region has reopened three years after being devastated by record flooding from ex-Tropical Cyclone Ellie in 2023, which destroyed tourism infrastructure and cultural sites. Restoration efforts involving debris removal, revegetation, and collaboration with Bunuba traditional owners have allowed limited access, though water access remains closed pending a feasibility study for boat tours.
The federal government has not ruled out additional voluntary water buybacks to address a projected 265 gigalitre shortfall in the Murray-Darling Basin Plan's water-saving target, after a draft report found state-run projects will fall significantly behind schedule. Minister Murray Watt emphasized the legislated obligation to meet science-based targets, while community leaders warned of devastating impacts on regional towns and food production from further buybacks.