The Kaikai Hydropower Station is the third level of the cascade of hydropower stations in the Kwanza River Basin, with a total installed capacity of 2,172 MW. The project aims to alleviate Angola’s electricity shortage and promote local economic development.
China News Service, Kunming, September 30 (Huangdi) China Energy Construction Gezhouba Group reported on September 30 that the lining concrete pouring of the tailrace tunnel No. 1, a key line and control project of the Angola Kaikai Hydropower Station project undertaken by the group, was completed 77 days ahead of schedule, marking that the tunnel has fully entered the consolidation grouting and ancillary engineering construction stage.
Kaikai Hydropower Station is located in Dondo City, Kwanza Norte Province, Angola. It is located in the middle section of the Kwanza River, the "mother river" of Angola. It is the third level of the eight-level cascade hydropower station in the basin. The power station has a total installed capacity of 2,172 MW, and the average annual power generation after completion will reach 8,566 GWh. It will meet more than 40% of Angola’s power supply needs, provide more than 6,000 local jobs during the peak construction period, and promote local economic and social development.
As an important part of the water delivery system of Kaikai Hydropower Station, the tailrace tunnel is connected to the tailrace pressure regulating chamber and externally to the Kwanza River. It assumes the core functions of transporting water flow and discharging the tailwater of the generating unit. The tailrace tunnel is divided into No. 1 and No. 2 holes. The two holes are arranged in parallel. The axis of the tunnel is 50 meters apart. The length of the tunnel is 5151.329 meters and 5179.469 meters respectively. Due to the large span, deep burial depth and long distance of the cavern, the lining construction has the characteristics of limited working space, frequent intersection of processes, and large amount of concrete pouring.
Since the opening of the first warehouse for concrete pouring, the tailrace tunnel construction team has scientifically coordinated the allocation of core resources of four types of trolleys: inverts, steel bars, linings, and grouting, and built an efficient production line with "inverts operating first, steel bars following simultaneously, linings in place accurately, and grouting seamlessly relaying." The project team also dynamically optimized the trolley transfer, positioning and disassembly processes to minimize non-operation time and strictly controlled the construction period of a single warehouse within 5 days to achieve interlocking and efficient connection of various processes.
During the construction of the project, the construction team implemented full-process monitoring of key parameters such as steel bar binding spacing, protective layer thickness, formwork flatness and stiffness, concrete mix ratio, slump and pouring vibration. Quality personnel work 24 hours a day, and rely on a digital and intelligent management and control platform to establish a traceability mechanism for the entire life cycle of quality issues. After testing, the size and appearance quality of the 371.6-meter lining completed this time met the design and specification requirements.
In order to ensure construction safety, in view of the complicated working conditions with intertwined risks such as high-altitude operations, hoisting, temporary power use, and vehicle traffic in the cave, the project department prepared special construction plans and emergency plans one by one, and continued to optimize the ventilation, lighting, and drainage operating conditions in the cave to achieve zero accidents in safe production throughout the entire cycle.
In the next step, the project team will steadily promote follow-up construction such as the consolidation grouting of the tailrace tunnel, the concrete pouring of the No. 2 tailrace tunnel lining, and the tailrace outlet.
AI outlook — possibilities, not facts
The project team will promote the consolidation grouting of the tailrace tunnel and the lining construction of the No. 2 tailrace tunnel
Very likely · Within months

Just under a third of Singaporeans, or 31.4 per cent, believe nuclear energy promises a clean power source with the greatest potential, marking the highest acceptance rate in Southeast Asia, according to a new survey.

Taiwan's offshore wind power phase 3-3 selection deadline ended on September 30. Only two companies, Woxu and CIP, submitted bids, and the total capacity did not reach the 3.6GW target. Due to the high degree of overlap between the two cases, it is expected that a winner-take-all situation will emerge, and the remaining capacity will be merged into the 3-4 phase selection. This investment promotion will cancel the mandatory localization and instead adopt ESG and local industry commitment selection.

On September 29, reporters accompanied the "Nuclear Safety Culture Media Tour" to visit the Hainan Nuclear Power Base Emergency Command Center in Changjiang, Hainan. After completing a new round of transformation, the center has become the base's "emergency center" and has the ability to coordinate emergency response for multiple reactor types and owners and fight against extreme situations such as super typhoons.
The "Xinjiang Electricity to Chongqing" ±800 kV UHV DC transmission project has transported more than 40 billion kilowatt-hours of electricity in total, injecting momentum into Chongqing's livelihood security and green development, and can reduce carbon dioxide emissions by 16.5 million tons every year.

The selection of candidates for Phase 3-3 of Taiwan's offshore wind power block development closed on the 30th. The Copenhagen Infrastructure Fund (CIP) announced the official submission of the tender for the Miemiao 3 offshore wind farm, demonstrating its determination to continue to deepen the Taiwan market.

In response to the demand for AI computing power, Minister of Economic Affairs Gong Mingxin said on the 30th that Taiwan will have 25 large-scale natural gas generating units online by 2035, with a device capacity of 26GW. Together with renewable energy, it can provide an additional annual power generation of 200 billion kilowatt-hours for computing power.