The government has selected semiconductors, physical artificial intelligence, and AI data centers as the 'three mega projects' and is emphasizing speed. However, delays in the construction of transmission and substation facilities according to the basic plan for power supply and demand continue, raising concerns about power supply disruption.
Rep. Eogyu said, “Power measures are needed for the success of the three major mega projects.”
(Seoul = Yonhap News) Reporter Jang Bo-in = It was found that more than 6 out of 10 transmission and substation facility construction projects according to the government's 7th to 10th Basic Plan for Electricity Supply and Demand (Electricity Basic Plan) were not completed in a timely manner.
While the government is emphasizing the speed of 'three mega projects' such as semiconductors, physical artificial intelligence (AI), and AI data centers, it is pointed out that special measures are needed to supply the necessary electricity on time.
According to data received from Korea Electric Power Corporation by Rep. Eogyu of the Democratic Party of Korea, a member of the Climate, Energy, Environment, and Labor Committee of the National Assembly on the 19th, out of 104 major transmission and substation projects of the 7th to 10th Electricity Report, 19 projects were completed within the target.
In 17 cases, the target date has not yet been reached, but in 68 cases, construction was completed beyond the target date or construction was not completed even after the target date was exceeded.
Excluding cases where the same project was included in the previous report multiple times and thus double-counted, there were 31 projects that exceeded the completion target. Of these, 15 have been completed after delays, but 16 have not been completed.
It was calculated that adding up all the excess periods for each of the 31 projects amounts to 121 years and 2 months (1,454 months).
The Bukdangjin-Sintangjeong transmission line was targeted for completion in June 2017, but was completed only in December 2024, and the Shinsongsan substation was also completed in December of last year, seven years later than the original target.
The Dongducheon C/C to Yangju transmission line, which was scheduled to be completed in April 2019, is still in the construction stage.
Looking at the current status of construction of transmission and substation facilities that KEPCO has been promoting for the past 20 years, including projects included in the electricity budget, a total of 283 projects are currently delayed, including 136 transmission towers and 147 substations.
The average construction period for facilities above 345kV (kilovolts) was about 10 years and 1 month for transmission towers and about 10 years for substations.
The reasons for the delay are also complex. The main reasons for the transmission tower project were civil complaints (40 cases), prior processes and related projects (31 cases), and permits (28 cases). In the substation project, industrial complex development and customer-related reasons accounted for the most with 49 cases.
Rep. Eo Gu-gu said, "In order to succeed in the three major mega projects, issues such as licensing adjustments, consultation with residents, and securing financial resources must be resolved to prevent industrial facilities from being unable to operate due to lack of electricity. The government must pool the capabilities of relevant ministries to come up with special measures to resolve power grid delays."
AI outlook — possibilities, not facts
The government will gather the capabilities of related ministries and prepare special measures to resolve power grid delays.
Likely · Within weeks

U.S. Secretary of Energy Chris Wright emphasized that the exemption from sanctions imposing high tariffs on countries purchasing Russian energy was an incentive to end the war, and argued that it was not an economic lifeline for Russia. President Trump waived the sanctions provisions of the Lindsey Graham Russia-Iran Sanctions Act, and Senator Darlene Graham, former Congressman Graham's sister, opposed it, insisting on maintaining pressure on Russia.

Due to the prolongation of the war in the Middle East, Korea's LNG imports from the Middle East decreased by 66.2% compared to the previous year from January to September of this year, while those from North America increased by 102.9%. In particular, Qatari products decreased by 68.6%, while American and Canadian products increased by 41.7% and 587.6%, respectively. The government is under pressure to participate in the Alaska LNG project and is pondering between strategic value and commercial feasibility.

US President Donald Trump stated that South Korea will invest $50 billion in an Alaska liquefied natural gas project as part of a trade and investment deal, despite Seoul's position that participation depends on commercial viability. He also claimed Taiwan agreed to invest $4.4 billion in the project and cited a White House official who said $54 billion is tied to the Alaska LNG project within a broader $200 billion South Korea energy investment package including nuclear plants and a Texas gas facility.

Regarding the integration of five public power generation companies promoted by the government, Ulsan City said that the location of the headquarters of the integrated corporation will become the national power industry control tower, and that Ulsan is the place where it can best realize its goals and strategies as the energy industry capital. Deputy Mayor for Economic Affairs Shin Min-sik emphasized the justification for hosting Ulsan based on its infrastructure such as floating offshore wind power, hydrogen economy ecosystem, and AI data center.

The Nuclear Safety and Security Commission will hold its 2026-16 meeting on the 15th to simultaneously submit for the first time the approval of the accident management plan for Kori Units 3 and 4 and the proposal for continued operation. The accident management plan is being reviewed for the third time, and the continued driving permit proposal is being submitted for the first time. The two nuclear power plants ceased operation in September 2024 and August 2023, respectively, and are expected to be restarted upon approval.

While the Ministry of Foreign Affairs raised the travel warning across Saudi Arabia to level 3, Ministry of Trade, Industry and Energy employees visited the site to strengthen energy cooperation. They are scheduled to arrive 26 hours after their flight was canceled and discuss cooperation in crude oil supply with Saudi Arabia.