Power system improvement construction process occurred… “Prepare measures to prevent recurrence”
A power outage occurred during power system improvement work at BEXCO Exhibition Hall 1 in Haeundae-gu, Busan, disrupting four exhibition events for 26 minutes.
AI-generated summary
BEXCO also experienced inconvenience to event officials and visitors due to a large-scale power outage in September 2023.
Power system improvement construction process occurred… “Prepare measures to prevent recurrence”
(Busan = Yonhap News) Reporter Son Hyeong-ju = A power outage occurred at BEXCO, an international exhibition and convention facility, in Haeundae-gu, Busan, disrupting some operations for 26 minutes.
According to Yonhap News coverage on the 29th, a power outage occurred at Exhibition Hall 1 at around 3:09 pm on this day.
At the time of the power outage, four exhibition events were in progress, including the Excellent Catering Industry Exhibition, Busan International Shoes, Textiles and Fashion Exhibition, and the 2026 Korea Architectural Culture Festival.
The power outage caused some disruption in exhibition hall operations.
Power outage was restored around 3:35 p.m.
BEXCO understands that a power outage occurred during system improvement work for power input into the exhibition hall.
A BEXCO official said, “We plan to thoroughly analyze the cause of the power outage and prepare measures to prevent recurrence.”
BEXCO also experienced inconvenience to event officials and visitors due to a large-scale power outage in September 2023.
![[Q&A] Korea Hydro & Nuclear Power said, “There will be no significant impact from replacing the Czech nuclear power plant contractor.”](/api/img?u=https%3A%2F%2Fimg.yna.co.kr%2Fetc%2Finner%2FKR%2F2026%2F10%2F29%2FAKR20261029198700003_02_i_P2.jpg&w=320&q=72&f=webp)
Korea Hydro & Nuclear Power announced on the 29th that contract negotiations with the Daewoo Engineering & Construction-Doosan Energy consortium, the construction company for the Dukovany nuclear power plant project in the Czech Republic, have finally collapsed. KHNP plans to select a new domestic construction company within July of next year.

Korea Electric Power Corporation (KEPCO) will hold the international power technology expo 'Bixpo 2026' at the Kimdaejung Convention Center in Gwangju from November 4th to 6th. This year, 198 companies will participate, and a new startup investment center will be established to support investment attraction and business cooperation.

Negotiations for a construction contract between Korea Hydro & Nuclear Power and the Daewoo Engineering & Construction-Doosan Energy consortium for the Dukovany nuclear power plant construction project in the Czech Republic broke down on the 29th due to differences of opinion on key terms. Korea Hydro & Nuclear Power began the process of selecting a new construction company, and Doosan Energy announced its intention to re-participate.

Korea Electric Power Corporation (KEPCO) said that suspending power cuts indefinitely for some Homeplus stores that have delinquent electricity bills is not fair and that it will review the situation of each store to decide whether to cut off electricity. However, measures to minimize damage to small business owners and sequential measures were announced.

The Korea Atomic Energy Research Institute and the UK National Nuclear Research Institute (UKNNL) signed an MOU for cooperation in private nuclear research and development at the IAEA Nuclear Energy Ministers' Meeting in Songdo, Incheon, on the 27th. The two organizations plan to cooperate in SMR and radioactive waste management.

Korea Hydro & Nuclear Power plans to sequentially restart Gori Units 3 and 4 in the first half of 2027 through facility improvement and maintenance following the Nuclear Safety and Security Commission's approval of the continued operation and operation change permit. Gori Unit 3 will operate until September 2034, and Unit 4 will operate until August 2035.