CNTrump pays close attention to Brazil's election, as Bolsonaro's son Cheng Lula challenges re-electionCNEuropean Countries Agree to Release Diesel Stocks Amid Iran WarESJunts overturns the Government's housing decrees and deepens its break with the ExecutiveKRThe government investigates the truth of Trump's statement about $8.4 billion in oil investment in Korea, saying, "There was no agreement."USNAZA: A Documentary Exposing the Mechanics of Airstrikes in GazaEUSeventeen EU nations oppose budget cuts to agriculture and cohesion fundsESPilot Smit Machchhar tells how he avoided an air tragedy after being stabbed by his co-pilotTRMass Opening of Security and Infrastructure Investments Held in YalovaTRMuhsin Rezai's reaction to Trump's statement 'We will destroy Iran'TRDecision in the 19-year-old murder case in Kahramanmaraş: Aggravated life sentences for two defendantsCNTrump pays close attention to Brazil's election, as Bolsonaro's son Cheng Lula challenges re-electionCNEuropean Countries Agree to Release Diesel Stocks Amid Iran WarESJunts overturns the Government's housing decrees and deepens its break with the ExecutiveKRThe government investigates the truth of Trump's statement about $8.4 billion in oil investment in Korea, saying, "There was no agreement."USNAZA: A Documentary Exposing the Mechanics of Airstrikes in GazaEUSeventeen EU nations oppose budget cuts to agriculture and cohesion fundsESPilot Smit Machchhar tells how he avoided an air tragedy after being stabbed by his co-pilotTRMass Opening of Security and Infrastructure Investments Held in YalovaTRMuhsin Rezai's reaction to Trump's statement 'We will destroy Iran'TRDecision in the 19-year-old murder case in Kahramanmaraş: Aggravated life sentences for two defendants
Back四川500千伏洪板一线完成改造,川渝电网输电能力增强
四川500千伏洪板一线完成改造,川渝电网输电能力增强
NEWS
中国新闻网yesterdayEnergy2 min readChinaView translation

四川500千伏洪板一线完成改造,川渝电网输电能力增强

Quick Look

10月1日,四川500千伏洪板一线完成综合改造并恢复投运。该线路全长148.77公里,是川渝电网间的关键联络线。此次改造通过优化施工方案,将原定3天的停电作业压缩至2天,保障了节日期间上万户民众的用电需求。

AI-generated summary

Why It Matters

洪板一线于1995年3月投运,是四川与重庆电网间8回联络线之一。由于运行时间超过30年,部分铁塔出现锈蚀老化,需进行技术改造。

Font size

中新网成都10月1日电(刘忠俊 王志奇 曾俊杰)10月1日,四川500千伏洪板一线完成综合改造和检修,线路恢复投运,工程正式竣工。

500千伏洪板一线输电线路四川段。王志奇 摄

洪板一线起于自贡洪沟500千伏变电站,止于重庆板桥500千伏变电站,全长148.77公里,其中四川段55.82公里,是四川电网与重庆电网之间清洁能源输送的8回联络线之一。线路1995年3月投运,至今已运行30多年,部分铁塔锈蚀老化,不再符合最新的运行技术标准,安全运行受到影响。

这次综合改造是2026年国网四川超高压公司秋检的重点工作之一。9月15日起,线路进入停电阶段,施工线路长40多公里,主要任务包括新建铁塔23基、安装耐张绝缘子96串和悬垂绝缘子63串、断紧线及弧垂调整8处、导地线挂点“单改双”6基塔位,还涉及“三跨”(跨越高速铁路、高速公路和重要输电通道)塔位施工等难度较大的项目。

改造中最让人头疼的是停电时间怎么安排。工程涉及110千伏武望线、武叙线等多条供电线路,窗口期只有3天,直接关系到上万户民众的节日用电。为此,国网四川超高压公司提前几个月就派人到现场勘查,主动与内江、自贡相关部门沟通协调,在关键环节、重点区域和特殊作业点增派现场监管和施工人员。最终,原本需要3天的作业被压缩到2天,相关线路赶在节前恢复带电,民众用电和施工安全都没耽误。

据悉,改造完成后,川渝电力输送通道更加安全可靠,两地之间的电能交换能力同步增强。

Open Questions

  • 改造后的具体输电容量提升数值是多少?

Related Topics

This article was originally published by 中国新闻网.

Related Stories

my country's first 100-megawatt compressed carbon dioxide energy storage project successfully connected to the grid
Energy·

my country's first 100-megawatt compressed carbon dioxide energy storage project successfully connected to the grid

On October 2, China Huadian’s Xinjiang Mulei 100-megawatt compressed carbon dioxide energy storage project was successfully connected to the grid. As the first large-scale project of its kind in my country, this project utilizes carbon dioxide gas and liquid interconversion technology to achieve peak shaving and valley filling of the power grid. It can store 290 million kilowatt hours of electricity per year and release 180 million kilowatt hours of clean green electricity to facilitate the construction of new power systems.

中国新闻网
4 min read
Lining pouring of No. 1 tailrace tunnel of Kaikai Hydropower Station in Angola completed ahead of schedule
Energy·

Lining pouring of No. 1 tailrace tunnel of Kaikai Hydropower Station in Angola completed ahead of schedule

The lining concrete pouring of No. 1 tailrace tunnel of Kaikai Hydropower Station in Angola, contracted by China Energy Construction Gezhouba Group, was completed 77 days ahead of schedule. The power station has a total installed capacity of 2,172 megawatts. Upon completion, it will meet more than 40% of Angola’s power supply needs and create a large number of local jobs.

中国新闻网
3 min read
Offshore wind power phase 3-3 supplier selection deadline: only Wo Xu and CIP bid, the total capacity did not meet the standard
Energy·

Offshore wind power phase 3-3 supplier selection deadline: only Wo Xu and CIP bid, the total capacity did not meet the standard

Taiwan's offshore wind power phase 3-3 selection deadline ended on September 30. Only two companies, Woxu and CIP, submitted bids, and the total capacity did not reach the 3.6GW target. Due to the high degree of overlap between the two cases, it is expected that a winner-take-all situation will emerge, and the remaining capacity will be merged into the 3-4 phase selection. This investment promotion will cancel the mandatory localization and instead adopt ESG and local industry commitment selection.

自由时报
2 min read
Visiting the Hainan Nuclear Power Base Emergency Command Center: Building a "hard-core fortress" for nuclear safety
Energy·

Visiting the Hainan Nuclear Power Base Emergency Command Center: Building a "hard-core fortress" for nuclear safety

On September 29, reporters accompanied the "Nuclear Safety Culture Media Tour" to visit the Hainan Nuclear Power Base Emergency Command Center in Changjiang, Hainan. After completing a new round of transformation, the center has become the base's "emergency center" and has the ability to coordinate emergency response for multiple reactor types and owners and fight against extreme situations such as super typhoons.