The International Arbitration Court has ruled on the claim regarding the construction of the Hanhikivi-1 nuclear power plant.
AI-generated summary
The contract for the construction of the Hanhikivi-1 nuclear power plant was signed in 2013. In May 2022, Fennovoima terminated the agreement.
The International Arbitration Court of the International Chamber of Commerce has declared Finland's unilateral termination of the contract with Rosatom for the construction of the Hanhikivi-1 nuclear power plant illegal, the Russian nuclear state corporation reported.
“Another victory for Rosatom ends a long-term legal battle between the Russian state corporation and the Finnish company Fennovoima. The International Arbitration Court of the International Chamber of Commerce (ICC) declared illegal the unilateral termination of the contract by the Finnish side for the construction of a nuclear power plant, the construction of which was carried out by Rosatom,” the statement says.
Rosatom noted the conclusions from this decision.
“The proceedings under the rules of the International Chamber of Commerce not only recognized the decision of the Fennovoima company as unlawful, but also recorded that on the date of termination the project was moving forward dynamically, and Rosatom companies were demonstrating progress in obtaining a license for the construction of nuclear power plants,” the message emphasizes.
The contract for the construction of the Hanhikivi-1 nuclear power plant in northern Finland was signed by Fennovoima and Rosatom in 2013 and envisaged the construction of one power unit with a capacity of 1,200 MW according to the latest generation 3+ project.
The volume of investment in the project was estimated at 7-7.5 billion euros, the volume of localization for companies from Finland and other EU countries was expected to range from 1.8 to 2.7 billion euros. The station was supposed to cover 10% of Finland's total electricity needs. However, in May 2022, Fennovoima terminated the contract, citing Rosatom’s alleged violation of project deadlines, as well as the worsening political situation.

The Second Court of Cassation rejected the appeal of Kirill Yakubovsky and Pavel Maslovsky against the verdict in the case of the theft of $126 million from the company V.M.H.Y. Holdings Limited. Meanwhile, the second criminal case involving the theft of more than 14 billion rubles is nearing its conclusion.

The Moscow City Court replaced the real seven-year sentence with a suspended one for Vyacheslav Portyannikov, convicted in the case of supplying low-quality body armor for the army and mediating a bribe.

The Moscow City Court replaced real imprisonment with a suspended one for Vyacheslav Portyannikov, convicted of mediation in bribery in the case of supplying low-quality body armor for the Ministry of Defense, taking into account his cooperation with the investigation, admission of guilt, age, awards and health.

The International Arbitration Court ICC declared illegal the unilateral termination by the Finnish company Fennovioma of the contract with Rosatom for the construction of the Hanhikivi-1 nuclear power plant in Finland.

The International Arbitration Court of the ICC declared illegal the unilateral termination by the Finnish company Fennovoima of the contract with Rosatom for the construction of the Hanhikivi-1 nuclear power plant. The final amounts of recovery will be determined by future courts.

Former billionaire Yulia Politsina lost her property and became homeless while trying to sell more than ten properties after her prenuptial agreement was found to be fictitious. The woman fell into a fraudulent scheme, as a result of which she lost her funds and housing.