AI-generated summary
AI data centers require continuous power for densely packed chips and cooling systems, and connecting new facilities to public electricity grids can take years. Global data-center electricity consumption is expected to nearly double from 485 terawatt-hours in 2025 to 950 in 2030, with AI-focused facilities projected to triple over the same period. New gas turbines take an average of six years to deliver in the United States, with global orders topping 100 gigawatts against manufacturers' estimated annual capacity of 60 to 70 gigawatts.
AI data-center developers are hunting for used gas turbines and retired jet engines because ordering brand-new power equipment could leave their servers waiting for electricity until the next decade.
Some companies are buying refurbished machines, while others are converting aircraft-engine technology into generators that can run alongside their computing facilities.
New gas turbines now take an average of six years to deliver in the United States, according to energy consultancy Wood Mackenzie. Delivery discussions are already focused on 2030 and 2031, a timeline that clashes with an AI industry trying to bring enormous computing campuses online much sooner.
Global turbine orders have topped 100 gigawatts, compared with manufacturers' estimated annual capacity of just 60 to 70 gigawatts, Reuters reported. Siemens Energy, GE Vernova, and Mitsubishi Heavy Industries have all said orders are outpacing what they can produce.
Gas turbines can generate large amounts of electricity by burning natural gas to spin equipment connected to a generator. AI data centers need that power around the clock to run densely packed chips and cooling systems, and connecting new facilities to public electricity grids can itself take years.
The International Energy Agency expects global data-center electricity consumption to nearly double from 485 terawatt-hours in 2025 to 950 in 2030. Consumption at AI-focused facilities is projected to triple over the same period.
From airplane engines to AI power plants
One way around the backlog is an aeroderivative turbine, a power generator built using technology adapted from aircraft jet engines.
Other companies are going further by seeking older machines and retired aircraft engines that can be rebuilt for stationary power production. For example, AI infrastructure firm Crusoe ordered 13 units from Missouri-based ProEnergy in April, each rated at 50 megawatts, for a combined 650 megawatts. The jet-engine-derived equipment is intended for future U.S. data centers, but the contract doesn't mean that Crusoe bought engines removed from retired aircraft.
Second-hand machines can also carry a substantial discount. Used turbines in good condition sell for about $1.5 million to $1.7 million per megawatt, compared with roughly $2 million to $2.5 million for new units, according to equipment brokers and energy analysts interviewed by Reuters.
One broker described a sale of two smaller turbines totaling 29 megawatts for $12.5 million. Equivalent new equipment would have cost about $35 million and taken five years to arrive, he said.
"That secondary market is very, very hot right now," EthosEnergy CEO Ana Amicarella told Reuters, adding that asking prices are climbing as more buyers compete for the same machinery.
The problem with second-hand power
Building a power plant beside a data center also brings fuel needs, air emissions, and permits into the equation. The Environmental Protection Agency says stationary turbines and engines used by data centers are subject to federal air-pollution standards.
Last week, OpenAI promised to cover electricity and grid costs at future campuses it owns and operates after voters backed tighter restrictions on data-center construction.
Power-market research firm Cleanview identified about 90 gigawatts of proposed on-site generation at U.S. data centers in its mid-2026 analysis. Only about 2 gigawatts was operating at the time
AI outlook — possibilities, not facts
Demand for refurbished gas turbines and aeroderivative generators will continue rising as AI data-center construction outpaces new equipment delivery.
Likely · Within months
Used turbine prices will continue climbing as more buyers compete for limited secondary-market inventory.
Likely · Within months

Anthropic released Claude Fable 5.2 and Mythos 5.2, AI models capable of building software and designing objects, with API pricing at $8 per million input tokens and $40 per million output tokens. Early tests showed projects costing up to $14,710, raising concerns about affordability for ordinary users.

North Korean hackers created at least six memecoins on the NEAR blockchain between Nov. 5 and 7 to launder roughly $430,000 stolen in the $6.4 billion Binance hack, according to Elliptic. The tokens attracted almost no outside trading and were abandoned shortly after launch. Elliptic also linked the same technique to the $1.5 billion Bybit hack in 2025, and reported that about 11.8 million NEAR worth $43.7 million remained unmoved at the time of analysis.

Google unveiled two new AI chips, TPU 8tx and TPU 8i Max, targeting privacy and memory-intensive workloads. The announcement comes as Nvidia shares fell following CEO Jensen Huang's admission of an affair with a woman suspected of spying for China.

North Korea-linked hackers are using self-created meme coins on Tron, Near, and Solana to launder a portion of the record $6.4 billion stolen from Binance, according to blockchain analytics firm Elliptic. The tactic breaks direct onchain links between thief and collector wallets but remains traceable, merely slowing investigators.

Bitcoin Lightning node operators remain exposed to CVE-2026-98432 despite LND software updates. While LND v0.20.7-beta and v0.21.6-beta disable MPTCP listeners, the underlying Linux kernel vulnerability requires direct patching to ensure full system security.

Coinbase's Base blockchain has retired Flashblocks data feeds in its Denim upgrade. Developers must migrate to new WebSocket RPC subscriptions, as old endpoints no longer provide data. The network is also investigating reports of transaction delays.