The "lattice pier" structure was used for the first time in China's railway engineering, marking an important technological breakthrough in the field of high pier bridge construction in mountainous areas.
AI-generated summary
The Wenmen-Mongolia Railway is approximately 116 kilometers long and is an important project along the southwest border in the national medium- and long-term railway network planning. The railway has a design speed of 160 kilometers per hour and is a national Class I dual-line passenger and freight electrified railway.
China News Service, Kunming, November 12 (Reporter Miao Chao) According to China Railway Kunming Bureau Group Co., Ltd., the construction of the No. 9 lattice pier of the Nanxi River Super Bridge on the Wenshan-Mengzi Railway in Yunnan (referred to as the "Wen-Mengzi Railway") was completed on the 12th. This is the first time that the "lattice pier" structure has been used in China's railway engineering, marking China's important technological breakthrough in the field of high pier bridge construction in mountainous areas.
The Nanxi River Super Bridge is located in Zhicun Town, Mengzi City, Yunnan Province. It has a total length of 789.71 meters and a maximum height difference between the bridge deck and the ground of 118 meters. It is the highest bridge on the entire Wenmeng Railway.
The bridge is located in an area with sharply undulating terrain, spanning deep ravines, and unfavorable geology such as dangerous rockfalls and karst development, making construction extremely difficult. Therefore, a total of 3 lattice piers were designed for the whole bridge. Among them, pier #9 is 105 meters high and is the highest pier on the entire line. The lattice structure is divided into 7 segments/176 pieces of assembly technology. The largest single component weighs 24 tons, which is like "building giant building blocks" at a height of 100 meters.
According to the relevant person in charge of the Southern Yunnan Railway Construction Headquarters of China Railway Kunming Bureau Group Co., Ltd., the concrete-filled steel tube lattice pier used this time is assembled into a trapezoidal pier with "wide at the bottom and narrow at the top" through steel pipes and I-beams. High-strength concrete is poured inside, which can save 30% to 50% of concrete and steel. At the same time, the prefabricated assembly process greatly reduces on-site pollution and construction risks, improves earthquake resistance and geological adaptability, and realizes the multiple values of cost reduction, efficiency increase, low carbon, and safety.
Cui Zhenxi, head of the first three bids project department of the China Railway 18th Bureau Wenmeng Railway Station, said that in order to ensure millimeter-level assembly accuracy of the 100-meter-level lattice piers, the project team specially laid out a high-level measurement control network, equipped with high-precision measuring instruments, and arranged a professional measurement team to conduct precision stakeout; during the construction, special technologies such as guide positioning and dynamic fine-tuning were simultaneously used, and multiple measures were taken to strictly control installation errors to ensure that the assembly accuracy of the guardrail fully meets the design standards.
The successful application of this lattice pier and the complete set of design, construction and full life cycle operation and maintenance technologies developed through this research are expected to provide a standardized technical model for other railway projects.
The Wen-Mongolia Railway is approximately 116 kilometers in length and has a designed running speed of 160 kilometers per hour. It is China's national Class I dual-line passenger and freight electrified railway. It is an important project of the southwest border railway in China's medium- and long-term railway network planning. After completion, it will further improve the structure of the road network in southeastern Yunnan and facilitate the travel of people of all ethnic groups along the route. It is of great significance to promoting high-quality economic and social development in border and ethnic areas and serving Yunnan's high-level opening up to the outside world.
The Philippine Presidential Palace said the government is prepared to respond to cyber attacks on government agencies. Previously, the National Privacy Commission confirmed that at least 10 government departments suffered cyber attacks and data breaches, involving millions of personal, business and administrative records.

Zhou Zhihe, deputy director of Taiwan's Cybersecurity Agency, said that hackers are increasingly using artificial intelligence to launch attacks around the world, and about 8 million personal data records have been affected in the past few weeks. The Bureau of Consular Affairs of the Ministry of Foreign Affairs disclosed that hackers invaded 72,702 passport photos and 26,072 scans of authorization letters, involving Taipei Geotechnical Engineering Office Facebook account, ezTravel, Taishin Bank, 91APP and other institutions.

The results of the 2026 AI Empowered Radio and Television Audio Innovation Application Competition were released in Nanning. The competition attracted 203 projects from China and ASEAN to participate, aiming to empower audio-visual content creation through AI technology and promote the dissemination and cultural exchange of Chinese film and television works in the ASEAN market.

The finals of the 2026 Hunan Provincial (International) Innovation and Entrepreneurship Competition opened in Changsha on November 12. 54 teams from home and abroad competed in the fields of new generation information technology, digital audio and video, etc., aiming to promote the transformation of scientific and technological achievements and the connection between investment and financing.

Semiconductor distributor Dalian University announced on the evening of the 11th that it had detected abnormal access to its internal system and confirmed that some employees' names and official email addresses had been accessed without authorization. The company has initiated contingency measures and currently assesses that neither financial nor business operations are affected.

The "Zhejiang Merchants Lingzhu Cup·College AI Application Innovation Challenge" sponsored by the Shanghai Zhejiang Chamber of Commerce kicked off in Shanghai. The competition sets 12 practical propositions for college students, provides AI points, training and a bonus pool of 10,000 yuan, aiming to select and cultivate young innovative talents who make good use of AI to create value.