Minister of Transport and Infrastructure Uraloğlu announced that the Çerkezköy-Kapıkule section will serve passenger and freight transportation.
Minister of Transport and Infrastructure Uraloğlu stated that with the Çerkezköy-Kapıkule section coming into service, Thrace will be included in the high-speed train network and travel times will be significantly shortened.
AI-generated summary
Çerkezköy-Kapıkule high-speed train line aims to connect Thrace to the high-speed train network and strengthen international corridors.
Stating that the Çerkezköy-Kapıkule section will serve both passenger and freight transportation, Uraloğlu said, "We are extending our high-speed train network from Çerkezköy to Kapıkule, all the way to the European border. With the commissioning of our line, we will include Tekirdağ, Kırklareli and Edirne in our high-speed train network, bringing Thrace together with the comfort of high-speed trains." he said.
Noting that the line was built in accordance with an operating speed of 200 kilometers per hour, Uraloğlu said, "Within the scope of the project we built as a double track, electric and Level-1 signal, we built 31 bridges, 8 cut-and-cover tunnels, 2 viaducts, 114 underpasses and overpasses and 175 culverts. We completed 353 kilometers of rail laying." he said.
Emphasizing that significant gains will be made in passenger and freight transportation with the completion of the Halkalı-Kapıkule High Speed Train Line, Uraloğlu said, "Passenger travel time between Halkalı-Kapıkule will decrease from 4 hours to 1.5 hours, and freight transportation time will decrease from 8.5 hours to 3.5 hours. We will increase the current line capacity by 4 times. Our annual passenger capacity will increase from 600 thousand to approximately 3 million, and our annual freight capacity will decrease from 1.5 million tons to 9.5 million." "It will increase to tons." he said.
Pointing out that Turkey's European railway connection will be strengthened with the commissioning of the Çerkezköy-Kapıkule section, Uraloğlu said, "Our Halkalı-Kapıkule Line is the most critical gate to Europe of the Central Corridor, which connects Turkey to the European railway network at high standards. We are strengthening the European connection of the railway chain that starts with Baku-Tbilisi-Kars and connects Asia and Europe with Marmaray." he said.
Stating that the line is located at the western end of the Development Road, which will start from the Favorite Port and extend to Europe via Turkey, Uraloğlu said that the project will further strengthen Turkey's position in the international transportation corridors on the east-west and north-south axis.
Stating that they built new station buildings in Babaeski, Lüleburgaz and Büyükkarıştıran within the scope of the project, and rebuilt Kapıkule and Edirne Train Station buildings, Uraloğlu said, "We are also implementing the Çerkezköy Freight Station Personnel Building and Loco Maintenance Workshop within the scope of our project. "We increased the number of roads in the Kapıkule Station area from 23 to 42, and the total line length from 14 thousand 840 meters to 29 thousand. We are increasing it to 680 meters. “We are making the approximately 2.4 kilometer section between Kapıkule and the Bulgarian border double-track.” He made a statement.
Today, there will be no fee on all integrated lines such as bus, metro, metrobus, ferry and rail systems in Istanbul. Istanbulites will be able to use these means of transportation without paying any fee throughout the day.

Minister of Transport and Infrastructure Abdulkadir Uraloğlu announced that the 153-kilometer Çerkezköy-Kapıkule section of the Halkalı-Kapıkule High Speed Train Line has been completed and will be opened on October 9.

GESTAŞ announced that some ferry services on the Dardanelles Strait and the Islands line have been canceled tomorrow due to adverse weather conditions in the north of the Aegean Sea. There will be no flights at certain hours on Kabatepe-Gökçeada and Geyikli-Bozcaata lines.

Minister of Transport and Infrastructure Abdulkadir Uraloğlu announced that work is continuing on the YHT Station-Esenboğa Airport Rail System Line, which will be 36 kilometers long and have 12 stations.

Bursa Sea Buses (BUDO) canceled 8 trips due to adverse weather conditions. The canceled flights were planned between Bursa (Mudanya), Istanbul (Kabataş) and Armutlu (İhlas).

Some cancellations were announced for İDO and BUDO voyages for citizens who will use sea transportation on September 28, 2026. While there was no general cancellation decision, some flights on Bursa and Istanbul lines were cancelled.