National Consumer Disputes Redressal Commission rules developer failed to secure OC for 18 years, leaving residents under threat of demolition.
AI-generated summary
The developer failed to secure an Occupancy Certificate for 18 years, leading to demolition threats for residents. The developer had constructed 45% more area than sanctioned.
A Mumbai housing society has been awarded Rs 6 crore in compensation after the National Consumer Disputes Redressal Commission (NCDRC) found that its developer handed over flats without an Occupancy Certificate (OC), leaving residents to live under the constant threat of demolition for 18 years.
The commission, comprising Justice A P Sahi and Bharatkumar Pandya, held the developer and its partners jointly and severally liable for deficiency in service, ruling that the absence of the OC was a continuing failure on the developer's part rather than any fault of the residents.
The developer had argued that the members themselves had carried out illegal construction in their units, which was blocking the OC from being issued. The commission rejected this claim, noting there was no evidence of it and that it was the developer who had promised, constructed and handed over the flats, including an additional 20% carpet area to original members, without ever securing the OC.
The bench held that it was the developer's responsibility to calculate the permissible construction, prepare valid building plans, get them sanctioned, and only then build accordingly, something it failed to do even after 18 years.
The commission found that the developer had raised close to 11,000 square feet more construction than what was sanctioned for the plot, nearly 45% in excess. It said this extra construction was done primarily to secure a larger share of free-sale flats for the developer's own profit, even at the cost of jeopardising the OC and causing prolonged distress to residents.
The commission noted that amended building plans were not even submitted until 2009, 2012 and 2021, and none of those attempts were seriously followed through.
The society had originally sought Rs 71 crore in compensation, based on a comparison between the area sanctioned in the approved plan and the area promised in the agreement. The commission called this claim exaggerated and unsubstantiated, pointing out that residents had accepted possession of their flats with full satisfaction over carpet area, and the real grievance was the missing OC and lack of a municipal water connection.
The commission calculated compensation at 1.5 times the rate stipulated in the original agreement, Rs 1 lakh per month for delay, applied across 218 months from June 2008 to August 2026, working out to Rs 324 lakh. It added Rs 26 lakh for the absence of a municipal water connection and extra municipal taxes, bringing the figure to Rs 350 lakh.
On top of this, the commission awarded a further Rs 250 lakh, citing the developer's failure to obtain the OC despite three applications and the prolonged agony and financial burden this placed on the society, bringing the total compensation to Rs 600 lakh (Rs 6 crore).
The commission has ordered the developer to obtain the OC within 12 months and hand it over to the society, with receipts from each of the 33 members. The compensation of Rs 6 crore must be paid within three months, failing which it will attract 8% simple interest until fully paid. The developer has also been directed to pay Rs 10 lakh towards litigation costs.
AI outlook — possibilities, not facts
Developer must pay Rs 6 crore compensation within three months.
Very likely · Within months
Developer must obtain Occupancy Certificate within 12 months.
Very likely · Within months
US District Judge Jeannette Vargas has invalidated a Trump administration policy that suspended immigrant visas for applicants from 75 countries, ruling the measure violates federal immigration law and exceeds the Secretary of State's authority.
Former Meta product design manager James Tillinghast is suing the company, alleging he was fired for refusing to sign an immigration support letter he deemed inaccurate and for raising concerns regarding unequal immigration assistance provided to certain employees.
Meta is on trial in Oakland, California, as 29 US states allege the company designed Facebook and Instagram to be addictive for minors, concealed internal research on mental health harms, and violated child privacy laws. The case could result in massive penalties.
A petition in India's Supreme Court challenges Bar Council of India Chairman Manan Kumar Mishra's prolonged tenure, seeking his removal, term limits, fresh elections, and an audit of BCI finances amid controversies.
A federal lawsuit filed by the estate of former Piedmont Airlines employee Niena Allen alleges a racially hostile work environment at Phoenix Sky Harbor International Airport, citing incidents including mocked George Floyd death, KKK imagery, and a noose.
Pravesh Aggarwal won a case in ITAT Delhi after being penalised Rs 3.74 lakh for failing to file his ITR on time due to missing Form 16 during a job switch, as TDS was already deducted.