Kuomintang Kaohsiung mayoral candidate Ke Zhien criticized the slow handling of the Yongan Waste Chai Mountain case. Kaohsiung City Councilor Qiu Junxian posted a photo to refute and explain the investigation timeline
Quick Look
- Kuomintang Kaohsiung mayoral candidate Ke Zhien criticized the handling of the Yongan Huai Chai Shan case for being too passive, questioning the need to wait for public submissions or a democratic investigation before taking action.
- Gao City Councilor Qiu Junxian issued an article detailing the timeline of the city's investigation, pointing out that the investigation was launched at the end of last year, transferred to the judiciary in February this year, smoldering was discovered and dealt with in July, the plan was required to be cleared in August, and the investigation and arrest work was emphasized as early as September.
- He criticized Ke Zhien's accusation of deliberate bias and called for respect for the professional dedication of the inspectors.
AI-generated summary
Why It Matters
About 13,900 tons of waste wood were illegally piled on agricultural land in Baoxing Section, Yong'an District, Kaohsiung City. It was called "Waste Wood Mountain" by the outside world, raising concerns about environmental pollution. The city government stated that it would launch an investigation in 2025 and deal with relevant operators in accordance with the law, requiring the removal to be completed by the end of 2026.
Kuomintang Kaohsiung mayoral candidate Ke Zhien issued an article criticizing the Yong'an Waste Chai Mountain case as "cannot wait for the civilian investigation to be handled"! Kao City Councilor Qiu Junxian's PO photo details the timeline of the city's investigation, emphasizing that it was handled at the end of last year and has been transferred to the judiciary, which is a slap in Ke's face.
About 13,900 tons of waste wood was illegally piled up on agricultural land in the Baoxing section of Yong'an District, Gao City, which was called "Waste Wood Mountain." The city government stated that it had launched an investigation in 2025, and later fined the perpetrators and related businesses involved in the case and brought them to justice. The deadline is to clear them all before the end of 2026. Ke Zhien issued an article criticizing that one piece of land after another has been destroyed. Is it necessary to wait for local people's petitions, representatives of the people to investigate, or even attract everyone's attention before starting to deal with it? Unacceptable.
Please read on...
Qiu Junxian said that of course environmental pollution cases must be strictly investigated and handled to the end, and the people's representative also has the responsibility to strictly supervise the city government; however, supervision must be based on complete facts and time series. A case that was investigated last year and transferred to judicial investigation at the beginning of this year cannot be described as "waiting for the investigation by the people's representative to start processing."
He laid out a timeline, explaining that the Environmental Protection Bureau took the initiative to launch an investigation at the end of last year, and took the initiative to transfer it to judicial investigation in February this year. On July 31 this year, it convened relevant industries to propose a cleanup plan, with a deadline to complete the cleanup before the end of the year. On August 1, the city’s AI cloud monitoring system discovered that the site was smoldering and producing obvious granular pollutants. The Environmental Protection Bureau immediately dispatched personnel to deal with it and punished it in accordance with the law. The waste wood on site was gradually removed.
He mentioned that the city government is investigating the flow of waste wood removal and has found out that 44 removal companies are involved in illegal disposal, of which 24 have obtained waste removal permits and 20 have not obtained permits. All of them have been transferred to judicial investigation in accordance with the law, and those involved in administrative responsibilities will also be investigated separately.
Qiu Junxian said that from the timeline, it can be seen that the case investigation, evidence collection, judicial transfer and subsequent clearance work were carried out one after another before September this year. Ke Zhien claimed that "every time he waited for local petitions and civilian investigations before starting to deal with the case", which was obviously deliberately biased and ignored the time and manpower investment required for the investigation.
He believes that where relevant units are not doing enough, the people's representatives certainly have the right to continue to demand improvements; but they should also respect the work of front-line inspectors in tracking down cases, collecting evidence, tracking down business operators, and transferring them to justice.
What to Watch
AI outlook — possibilities, not facts
Kaohsiung City Environmental Protection Bureau will complete the removal of all waste wood from Yongan Waste Wood Mountain by the end of 2026
Likely · Within months
Open Questions
- How is waste wood ultimately disposed of?
- Will the businesses involved face criminal liability?
- Will the city government strengthen its monitoring mechanism for illegal accumulation of agricultural land?