RUIsraeli security forces urgently evacuate Netanyahu's son from the United StatesITDe Zerbi loses his second consecutive match with Tottenham: 0-2 against NewcastleCNSoldiers mutiny in Niger, military junta says it has regained control of the situationTRA motorcycle driver without a license plate tried to escape from the police in Akçakale and was detainedUSMilo Yiannopoulos Arrested and Deported for U.S. Immigration ViolationsITNiger's military regime recaptures a military base in Niamey with Russian helpINTLLos Angeles Rapper ColdheartedAC Arrested in $8.1 Million Stolen-Check SchemeJPSpecial heavy rain warning announced in Fukui Prefecture, record rainfall continuesRUExplosions occurred in Kyiv, residents are preparing for shellingUKElversberg stun Leverkusen 3-2 in Bundesliga debut as other European leagues see mixed resultsRUIsraeli security forces urgently evacuate Netanyahu's son from the United StatesITDe Zerbi loses his second consecutive match with Tottenham: 0-2 against NewcastleCNSoldiers mutiny in Niger, military junta says it has regained control of the situationTRA motorcycle driver without a license plate tried to escape from the police in Akçakale and was detainedUSMilo Yiannopoulos Arrested and Deported for U.S. Immigration ViolationsITNiger's military regime recaptures a military base in Niamey with Russian helpINTLLos Angeles Rapper ColdheartedAC Arrested in $8.1 Million Stolen-Check SchemeJPSpecial heavy rain warning announced in Fukui Prefecture, record rainfall continuesRUExplosions occurred in Kyiv, residents are preparing for shellingUKElversberg stun Leverkusen 3-2 in Bundesliga debut as other European leagues see mixed results
Back桃園捷運棕線先期工程啟動 打造北北桃一小時生活圈
桃園捷運棕線先期工程啟動 打造北北桃一小時生活圈
Developing
自由时报7/12/2026Transportation2 min readChinaView translation

桃園捷運棕線先期工程啟動 打造北北桃一小時生活圈

Quick Look

桃園捷運棕線(桃園-龜山-迴龍段)先期工程已啟動,全長約11.38公里,設7座車站。完工後,桃園車站至新北迴龍站最快約18分鐘,串聯多條軌道路網,打造北北桃一小時生活圈。

AI-generated summary

Font size

捷運棕線是桃園交通建設的重要里程碑,不僅有助提升桃園與龜山地區交通機能,也可有效縮短往返雙北的通勤時間。(圖/桃園市政府提供)

桃園捷運路網再跨出重要一步。「桃園捷運棕線(桃園-龜山-迴龍段)先期工程開工典禮」近日正式啟動先期工程,未來全線完工後,從桃園車站至新北迴龍站最快約18分鐘,可串聯台鐵、機場捷運、桃園捷運綠線、新蘆線及萬大線等軌道路網,進一步打造北北桃一小時生活圈。

桃園市市長張善政表示,捷運棕線是桃園交通建設的重要里程碑,不僅有助提升桃園與龜山地區交通機能,也可有效縮短往返雙北的通勤時間。路線自迴龍出發,沿線行經龍華科技大學、桃園巨蛋周邊,並銜接桃園火車站,未來通車後可望大幅提升交通便利性,改善市民通勤效率。

他指出,市府持續推動桃園捷運路網建設,除全力朝捷運綠線北段年底通車目標邁進外,棕線後續也將延伸至市府第二行政園區,並串聯橘線等捷運路網,逐步建構更完整的大眾運輸系統。

桃園市政府捷運工程局表示,捷運棕線全長約11.38公里,共設置7座車站,包括5座地下站及2座高架站,路線由桃園車站出發,行經桃園區、龜山區,銜接至新北市迴龍地區。未來除可縮短桃園往返雙北通勤時間,也將串聯多條既有及規劃中的軌道路網,提升整體公共運輸效能。

捷工局指出,捷運棕線綜合規劃已獲中央核定,總經費約456億元。此次先期工程範圍自BR02站至BR08站,工期約270天,將辦理沿線騎樓打通及整平、集社陸橋人行天橋拆除、植栽移植等作業,提前改善人行環境並降低後續主體工程施工衝擊,也為捷運棕線正式施工奠定基礎。