As Chubu Electric Power moves forward with decommissioning work at Hamaoka Nuclear Power Plant Units 1 and 2, suspicions have surfaced of inappropriate rewriting of construction reports and fraudulent expense claims.
On the 25th, Chubu Electric Power announced that four new cases of inappropriate rewriting of construction documents related to Units 1 and 2 during decommissioning work at the Hamaoka Nuclear Power Plant (Shizuoka Prefecture) were discovered, bringing the total to 18. In order to make it appear that things were progressing according to plan, they made reports that differed from actual results. An investigation will continue to determine the extent to which costs were overcharged.
The inappropriate procedures surrounding the decommissioning of the reactor were discovered in late August. The Ministry of Economy, Trade and Industry requested an investigation into the facts and causes, and Chubu Electric Power made a report on the same day.
According to the report, 18 construction reports that Chubu Electric submitted to the Spent Fuel Reprocessing and Decommissioning Organization (NuRO) as evidence of decommissioning costs in fiscal 2024 were rewritten. Although no changes were made, there were some documents that did not match Chubu Electric's internal data, and there was a possibility that expenses were fraudulently claimed in a total of eight cases.
According to Chubu Electric, six people were involved in the rewriting. In addition to adding seal impressions that were not filled in, they also reported information that differed from actual results in order to make it appear that the construction was progressing as planned. During the plan formulation stage, NuRO received many points, and the idea was that ``if things don't go as planned, we will lose credibility and it will be difficult to receive payments.'' There was also a ``feeling that they couldn't go against the officials'' who ordered the rewriting.
The group that is the contractor for the construction...
AI outlook — possibilities, not facts
Continuation of investigation into overcharged amount by Chubu Electric Power and additional report
Very likely · Within weeks

Tokyo Electric Power Co., Ltd. and Japan Atomic Power Co. have proposed a new plan for an interim storage facility in Mutsu City, Aomori Prefecture, in which Kansai Electric Power and Tohoku Electric Power will participate. Aiming to secure 5,000 tons as originally planned, it is assumed that delivery will begin around 2028. Prefectures and cities will now decide whether to accept them.

Chubu Electric Power President Kingo Hayashi held a press conference in Nagoya on the 14th and announced the withdrawal of the application for restart review of Hamaoka Nuclear Power Plant Units 3 and 4. Although he apologized for the fraud issue, he emphasized his stance of maintaining the nuclear power plant and indicated that he would aim to reapply.

On the 14th, an external investigation committee into the Chubu Electric Power Hamaoka Nuclear Power Plant's earthquake estimation data fraud issue released a report stating that criticism and reprimands by management for the delayed review led those in charge to act inappropriately. The company announced the withdrawal of its application for restart examination of Units 3 and 4, and the resignation of President Kingo Hayashi and Chairman Satoshi Katsuno.

It has been revealed that Chubu Electric Power is considering withdrawing the review of Hamaoka Nuclear Power Plant Units 3 and 4 due to data fraud issues surrounding the review. The results of the third-party investigation will be announced on the 14th, and management will hold a press conference. The outlook for restarting operations is uncertain.

Regarding the Alaska LNG Project, which transports natural gas from northern Alaska to the south and exports it as LNG, Dr. Watson from the University of Alaska talked about competitiveness in the Pacific region market and his expectations for Japanese companies' participation in the project in an interview with Jiji Press.

In Europe, where record-breaking heatwaves continue, multiple nuclear power plants have been affected, including the Paks nuclear power plant in Hungary, which has shut down due to a lack of cooling water due to falling river levels. On the other hand, since Japan uses seawater, domestic power companies have explained that they are not affected by similar heatwaves.