Jianmiaoyi will fight to supply power to 6 major technology manufacturers next year. Jianmiaoer will complete financing before June next year.
The Jianmiao Second Wind Farm plans to complete project financing before June next year, and CIP emphasized that it will continue to participate in the subsequent selection of offshore wind power suppliers.
Quick Look
- Copenhagen Infrastructure Fund (CIP) announced that its Jiaomiaoyi offshore wind farm is expected to be completed and connected to the grid next year, and will supply green power to six major manufacturers including MediaTek and Google.
- At the same time, the financing for the Jianmiao Second Wind Farm project is expected to be completed before June next year, and CIP will continue to participate in the subsequent wind farm selection.
AI-generated summary
Why It Matters
CIP has been allocated multiple wind farms in the development of offshore wind power blocks in Taiwan and is currently actively promoting the construction and financing of the Jianmiao series of wind farms.
The 500MW Miemiao 1 wind farm allocated by CIP (Copenhagen Infrastructure Fund) in the 3-1 phase of the offshore wind power block development is expected to be completed and connected to the grid next year, and will be online to supply green power to six major technology companies, including China Microelectronics, UMC, Far EasTone, Taiwan Columbia, MediaTek and Google. As for the Miemiao 2 wind farm allocated in the 3-2 phase, CIP managing director Xu Naiwen said today (14th) that the project financing is planned to be completed before June next year.
Inventorying the development of wind farms, CIP pointed out that the Jiemiao One Wind Farm was allocated 500MW in the first place in the 3-1 phase of block development. It is expected to be completed and connected to the grid in 2027. Financing has been successfully secured. Power purchase customers include 6 major technology companies, including China Microelectronics, UMC, Far EasTone, Taiwan Columbia University, MediaTek and Google.
The Jianmiaoyi Wind Farm uses 33 Vestas V236-15MW wind turbines. Offshore construction operations have been started since February this year. All 99 underwater foundation piles have been installed. The onshore and offshore substations have completed power transmission last month and this month respectively. The installation of 14, more than 1/3 of the casing underwater foundations has been completed. Xu Naiwen said that Jiaomiaoyi Wind Farm will take advantage of the climate window construction that is about to end this year.
The Feng Miao Er Wind Farm has been allocated an installation capacity of 600MW in Phase 3-2 and is expected to be completed in 2030. Electricity sales arrangements, project financing and construction permits are still in progress. Xu Naiwen said that Feng Miao Er plans to complete the project financing before June next year.
CIP is bidding for the 806MW Jianmiao San Wind Farm in Phase 3-3, and the selection results will be announced at the end of the year. CIP emphasized that from the second phase of offshore wind power potential sites to the third phase of block development, no matter how Taiwan's offshore wind power development environment changes, CIP will always "go against the current and never be absent." CIP still has 6 wind farm projects in hand and will continue to participate in the follow-up selection of companies, including the three wind farms that have passed environmental impact assessments: Jiefan, Jiecheng, and Jieli.
What to Watch
AI outlook — possibilities, not facts
Jiaomiaoyi wind farm will be completed and connected to the grid in 2027
Likely · Within years
Jie Miao Second Wind Farm will complete project financing before June next year
Likely · Within months
Open Questions
- What are the results of Jianmiao Sanfeng Farm’s business selection?