该工程将提升新疆北部地区能源保供水平,补齐当地电网短板
新疆塔城托里2×66万千瓦煤电项目750千伏送出工程于10日全线贯通。该工程新建线路39.297千米,旨在提升北疆地区电网承载力,保障煤电项目按期投运,满足区域用电增长需求。
AI-generated summary
塔城中西部地区此前长期依赖220千伏电网,网架承载力有限,难以承接大型电源落地。该工程旨在解决当地电网短板。
中新网乌鲁木齐11月11日电 (马叶叶 高亮 姜勇 赵明)新疆塔城托里2×66万千瓦煤电项目750千伏送出工程10日实现全线贯通。这项工程为配套煤电项目按期投运创造条件,进一步提升新疆北部地区能源保供水平。
据了解,该工程2025年8月开工,新建线路39.297千米,架设铁塔103基,主要服务托里煤电项目接入新疆750千伏主电网。此前,塔城中西部地区长期依靠220千伏电网供电,网架承载力有限,难以承接大型支撑性电源落地。工程建成后,将补齐当地电网短板,满足区域用电增长需求。
工程全线穿行老风口、玛依塔斯风区,区域年均8级以上大风天数超150天,高空架线、基础锚固、导线防护挑战巨大;线路途经冲洪积平原、低山丘陵,地质条件复杂,桩基施工难度高;沿线交叉跨越密集,部分区段集中叠加多处跨越,是全线最大施工难点。
建设团队多措并举破解施工难题,采用加强型铁塔、V型防风串、瓷质绝缘子提升线路抗风性能。“针对高路基跨铁路、高速及多条电力线路的安全风险,我们采用全档封网跨越、停电配合施工,铁路跨越段按‘一档一区段’组织架线,压缩高风险作业范围;逐塔复核地质条件动态调整基坑方案,严格执行大风预警停工机制,错峰开展组塔、架线,抢抓有效施工窗口期。”新疆送变电公司输电施工分公司项目经理高亮介绍,项目同步增配人员机具,全力应对风区恶劣天气带来的工期压力。
下一步,国网新疆电力将抓紧开展线路消缺等收尾工作,紧盯投运节点,保障工程按期送电,持续为北疆能源稳定供应和地方经济高质量发展提供支撑。
AI outlook — possibilities, not facts
国网新疆电力将开展线路消缺及后续投运工作
Very likely · Within months

A DLA Piper report reveals that 23% of energy-sector stakeholders have cancelled or delayed viable storage projects due to unpredictable mineral pricing, which is heavily tied to Chinese-influenced benchmark indices.

With U.S. President Trump suspending military action against Iran, the U.S.-Iran conflict has fallen into a situation of no war and no peace. Reuters analysis pointed out that although the energy-producing countries in the Persian Gulf have gradually adapted, continued conflicts and maritime attacks still lead to high operating costs and insurance premiums, posing long-term risks to the energy industry.

Affected by the cold air, the demand for heating coal in northern my country is strong. Coal production bases such as Shanxi, Inner Mongolia and Xinjiang have increased production. The railway department has made simultaneous efforts through Tangbao, Daqin, Wari, Xinshuo and other railways and multiple Xinjiang coal transportation channels. There are 80 Xinjiang coal export trains with a transportation capacity of 300,000 tons every day, making every effort to ensure smooth thermal coal transportation in winter.

A fire broke out in a garbage dump near Hengchun Nuclear Plant No. 3 in Pingtung. The plant clarified that the fire was far away from the core units and would not affect nuclear energy safety. It also emphasized that the notification mechanism has been improved and fire safety will continue to be strengthened.

The concrete pouring of the first tank of the nuclear island of Unit 4 of CGN Zhejiang Sanao Nuclear Power Project has started, marking the official start of the main project and the second phase of the project entering full construction. The unit uses the "Hualong One" third-generation nuclear power technology. After completion, it is expected to generate 9 billion kilowatt-hours of electricity annually, which can meet the electricity needs of about 1 million people.

As of November 10, Zhejiang's inter-provincial spot electricity purchases in 2026 reached 10.427 billion kilowatt hours, accounting for 24% of the national transaction volume. Zhejiang uses an artificial intelligence-assisted decision-making system to cope with fluctuations in new energy sources and peak power balance pressures within the province through mutual aid between provinces, and has purchased more than 10 billion in electricity for three consecutive years.