The stormwater sewer improvement project on Shanghai Road in Taoyuan City is completed, using excavation-free construction methods to improve flood control resilience
Quick Look
- The Taoyuan City Water Affairs Bureau completed the stormwater sewer improvement project on Shanghai Road in Pingzhen District.
- It used SPR lining and excavation-free construction methods to repair an old box culvert that was more than 30 years old.
- The total length is about 130 meters and serves a 120-hectare water catchment area.
AI-generated summary
Why It Matters
The Taoyuan City Water Affairs Bureau is responsible for maintaining the city's stormwater sewer system. Faced with the challenges of old facilities and frequent heavy rainfall brought about by climate change, it actively promotes the renewal of flood control projects and facilities.
The Taoyuan City Water Affairs Bureau is handling the "Shanghai Road Stormwater Sewer Improvement Project in Pingzhen District". The picture shows a comprehensive inspection of the old box culvert before construction for reinforcement. (Photo provided by Taoyuan City Water Conservancy Bureau)
There is a lot of effort in urban flood control hidden in the invisible ground! The Water Affairs Bureau of the Taoyuan City Government carried out the "Shanghai Road Rainwater Sewer Improvement Project in Pingzhen District" to improve the aging and damage of the existing rainwater sewer box culvert. It completed the repair of the existing double-hole box culvert, with a total length of about 130 meters. It strengthened and extended the life of the old facilities to improve drainage efficiency and reduce the risk of flooding.
Director of Water Affairs Liu Zhenyu said that the biggest highlight of this project is that it can "renew" the old box culvert that is more than 30 years old without large-scale road excavation. The Water Bureau uses the SPR lining construction method to directly repair and reinforce the existing box culvert. This not only eliminates the need for traditional excavation, backfilling and other construction procedures, shortens the construction period, but also significantly reduces the construction scope, reduces road closures, and maintains smooth ground traffic. The project started on October 3 last year and was successfully completed on August 21 this year. During the more than 10 months of construction, the Shanghai Road drainage box culvert still adhered to its position to maintain smooth drainage, serving the 120-hectare water collection area without any flooding problems due to construction.
Please read on...
Liu Zhenyu mentioned that rainwater sewers are usually hidden under the roads and cannot be seen, but they are an important line of defense to protect the city when heavy rains come. After the completion of this repair, the damage to the existing box culvert can be improved, the drainage function can be restored and improved, and the flood control resilience of the area around Shanghai Road can be further enhanced.
Liu Zhenyu emphasized that in the face of the increasingly frequent short-duration heavy rainfall, the Water Affairs Bureau continues to promote the construction of rainwater sewers and the improvement of old facilities, and introduces appropriate construction methods according to different local conditions, so that the ground will be less painful during construction and the underground will be more flood-proof and resilient. The city's drainage network will be repaired section by section so that when the next heavy rain comes, the water will go its own way and the citizens will go their own way.
The Taoyuan City Water Affairs Bureau is handling the "Shanghai Road Rainwater Sewer Improvement Project in Pingzhen District". The picture shows the low-pollution construction without excavation equipment during the construction. (Photo provided by Taoyuan City Water Conservancy Bureau)
The Taoyuan City Water Affairs Bureau is handling the "Shanghai Road Rainwater Sewer Improvement Project in Pingzhen District". The picture shows the gorgeous turn of the drainage box culvert after the construction. (Photo provided by Taoyuan City Water Conservancy Bureau)
Open Questions
- What is the total budget for this project?
- Are there plans to carry out similar improvements to older box culverts in other areas?
- How durable is the SPR lining construction method in long-term use?