Via Campo will begin modernization works on BR-163 from April 2026, including duplication, marginal roads, diamond and parclo intersections, U and
AI-generated summary
Via Campo took over the BR-163 concession in April 2026, responsible for the operation, maintenance and modernization of Lot 5 of the Integrated Highways of Paraná, which covers 433 kilometers of federal and state highways in the West and North regions of the State.
BR-163 is among the highways that will undergo modernization works during the Via Campo concession. - Disclosure/Via Campo.
Advertising Special
BR-163 will undergo modernization works to increase safety and fluidity
Duplications, marginal roads, intersections and new devices are planned throughout the first years of the highway concession.
By Via Campo
Since the beginning of the BR-163 concession, in April 2026, Via Campo has worked on the recovery, conservation and signaling of the highway, in addition to the implementation of the Operational Service Bases (BSOs) and the restoration works on the Ayrton Senna Bridge, in Guaíra (PR).
In addition to the services that are already being carried out, BR-163 will undergo a series of modernization interventions throughout the first years of the concession. The concessionaire's planning includes duplication works, implementation of marginal roads, diamond intersections, parclo-type devices (partial interchange), U-turns, wildlife crossings and the Guaíra Contour.
These interventions are part of a set of actions provided for in the concession contract and aim to increase safety, improve traffic flow and modernize the BR-163 infrastructure.
"The concession represents an important change in the infrastructure standard of BR-163. We are talking about a set of interventions that, over the next few years, will contribute to a safer, more efficient highway prepared to meet the mobility and development demands of the region", says Pedro Veloso, Engineering director at Via Campo.
Sections of BR-163 will receive interventions to increase safety and improve traffic flow. — Photo: Disclosure/Via Campo.
First stage
In the first stage, it is planned to build 1.32 km of marginal roads between km 197.6 and 236.2, with completion scheduled for April 2029.
The stretch will also receive a trumpet work, at km 212.2, concave curve lighting, at km 214.6, two parclo-type devices, at km 218.6 and 232.5, and a U-turn, at km 223.87.
Second stage
Between km 236.2 and 248.4, two U-turns will be built, at km 236.53 and 240.38, in addition to an OAE (Special Work of Art) at km 239.86. Completion is scheduled for April 2030.
In the section between km 276.8 and 301.9, 16.2 km of duplication and 1.7 km of marginal roads are planned. Three diamond-type devices will also be implemented, at km 293.58, 298.94 and 301.9, in addition to a fauna crossing.
The second stage also includes the Guaíra Contour, 3.71 km long, a trumpet work and two diamond-type devices, at km 1.66 and 3.58.
Third stage
The third stage foresees 13.3 km of duplication and 1.1 km of marginal roads, between km 301.9 and 315.2.
Two X-turns are also scheduled, at km 304.88 and 313.24, an elongated roundabout, at km 307.65, and an OAE (bridge over the Guaçu River), at km 311.4. The completion of this stage is scheduled for April 2031.
BR-163 is part of Lot 5 of the Integrated Highways of Paraná and will have duplication works and the implementation of new devices. — Photo: Disclosure/Via Campo.
Fourth stage
Between km 315.2 and 343.9, 28.7 km of duplication will be carried out and a diamond-type device will be implemented at km 318.7. The interventions are expected to be completed by April 2032.
The stretch will also receive returns at X and an OAE (bridge over the Tatuí River), at km 340.35.
Investments
Via Campo is responsible for the operation, maintenance and modernization of Lot 5 of the Integrated Highways of Paraná, which covers 433 kilometers of federal and state highways in the West and North regions of the State.
Rodovia BR-163 will have different interventions foreseen in the concession contract over the next few years. — Photo: Disclosure/Via Campo.
Over the 30 years of the concession, more than R$11.8 billion in investments are planned. Of this total, approximately R$6.7 billion will be allocated to expansion works and structural improvements and around R$5.1 billion to the operation and maintenance of the road network.
content under the responsibility of the advertiser

The BR-116 and BR-251 highways implement the 'free flow' toll system, which carries out automatic collection without stopping. The change includes partial and total closures on the runway for equipment installation, with full release scheduled for 4pm.

Residents of the Vitória neighborhood protest against the precarious state of the streets, demanding paving and improvements. The city hall promised to hear the demands next Tuesday.

Port authority will open office in Santos within 30 days to serve residents affected by the immersed tunnel project between Santos and Guarujá, an investment of R$6.8 billion.

Simão Pereira and Comendador Levy Gasparian agreed to transfer the BR-040 toll plaza to km 831, with the expectation of adopting the free flow system.

More than 300 areas of Manaus will have water supply interrupted this Wednesday due to preventive maintenance at the Ponta do Ismael Water Treatment Plant. Full water return can take up to 48 hours.

Bridge widening works on the BR-050 in Cristalina, Goiás, cause closures and the stop and go system. Access via Rua Doze-A is closed. Work lasts 60 days and aims to add shoulders and sidewalks.