It marks the key progress in the construction of the north-south transportation axis of Huizhou's "feng" traffic main framework.
AI-generated summary
The total length of the Huixia Expressway is approximately 69.9 kilometers. It is a key project on the north-south traffic axis of Huizhou City. The Dongjiang Super Bridge is the most difficult control project to construct along the entire line.
China News Service, Guangzhou, September 26 (Reporter Cai Minjie) The Guangdong Transportation Group announced on the 26th that the Hui (Cheng) Xia (Yong) Expressway Dongjiang Super Bridge has completed the closure of the entire bridge. The east and west sides of the bridge "reunion" on the 25th during the Mid-Autumn Festival, marking key progress in the construction of the north-south transportation axis of Huizhou's "Feng" traffic main framework.
The Huixia Expressway has a total length of approximately 69.9 kilometers and is a key project on the main north-south traffic axis of Huizhou City. After the project is completed, it will connect Shenhai Expressway and Huida Expressway to form a transportation artery from Huicheng District to Daya Bay Economic and Technological Development Zone, further improve the expressway network in the Guangdong-Hong Kong-Macao Greater Bay Area, and inject strong momentum into the high-quality development of the region.
The Dongjiang Super Bridge is the most difficult control project to be constructed along the Huixia Expressway. It adopts a single-tower steel box girder cable-stayed bridge design. The total height of the bridge tower is 172 meters, which is currently the highest bridge tower in Huizhou. The bridge is 57.5 meters wide, built to a two-way eight-lane standard, with sidewalks and non-motorized lanes set up simultaneously, and spans the Dongjiang Channel.
The main tower of the bridge adopts the shape of the ancient Chinese character "Feng". The 102-meter range of the upper tower column is a steel shell-concrete composite cable tower, and the 70-meter range of the middle and lower tower columns is a concrete tower. There are 21 pairs of stay cables on one side. The structure is novel and the construction is difficult.
The steel box girder of the Dongjiang Super Large Bridge has a total of 49 segments, with a total length of 566 meters. The girder segments are wide and heavy, making it difficult to hoist and match. It puts forward high requirements for single segment line matching and full bridge line control.
Steel box girders are processed at the Zhongshan and Shanwei bases, and ships enter the Dongjiang River through the Pearl River Estuary, passing through many maritime jurisdiction waters such as Zhongshan, Dongguan and Huizhou. They are restricted by the "daytime upward and nighttime downward" traffic control of the Dongzhou River Bridge in the Guangzhou-Shenzhen Expressway Expansion (Dongguan Section), the complex navigation conditions of tugboat escort in the Shilong Section of Dongguan, the width and height restrictions of the Huizhou Jiantan Ship Lock, and the tidal passage of the downstream shoals. The project team communicated and coordinated with various maritime, waterway, ship lock and other units in advance to increase transport ships and plan transportation time to meet on-site lifting requirements.
Then there are the problems of positioning, assembly, and welding. The width of the steel box girder of the Dongjiang Extra Large Bridge is 57.5 meters. To this end, the project processing base uses long-line method matching, combines three-dimensional laser scanning technology to generate real models of components, and pre-assembles to ensure the splicing effect of the beam surface; at the same time, Beidou + GNSS real-time dynamic monitoring is used on site to achieve millimeter-level accuracy in splicing each segment.
After the Dongjiang Super Large Bridge is closed, the project department will promote the bridge deck paving and installation of bridge ancillary facilities. Once completed, the project will be of great significance in serving Huizhou’s urban area and promoting economic development along the route.

The finale of the "2026 Summer Festival Fresh Market" "Come to Qishan" will be held at Qishan Stadium on the 26th. Mayor Chen Qimai personally prepared cross-border co-branded dishes and pointed out that Qishan bananas are a secret weapon to promote the city’s diplomacy and strive for construction, demonstrating Kaohsiung’s excellent export performance of agricultural products.

South Korea has set off a boom in stock buying by minors. As of the end of last year, nearly 770,000 minors held shares of listed companies, a sharp increase from 2019. Parents and financial institutions have launched financial education for children, but the risks of minors engaging in margin trading have also attracted the attention of the authorities, who are pushing for legislation to ban it.

Canadian nuclear fusion company General Fusion is listed in the United States, becoming the first publicly listed nuclear fusion company in human history. The company uses exclusive magnetic target fusion technology and is expected to connect the first commercial nuclear fusion power plant to the grid between 2035 and 2040.

In recent years, China's consumer market has seen emerging scenarios such as emotional consumption and experiential consumption, which are inseparable from the promotion of private enterprises. Experts pointed out that private enterprises, relying on their flexible mechanisms and innovative advantages to accurately understand market demand, have become a key force in promoting the continued renewal of China's consumer market.

This year’s Mid-Autumn Festival has four consecutive days of fine weather and stable weather. Statistics from the Ministry of Transport show that land, sea and air traffic have grown across the board. Among them, high-speed rail traffic exceeded 340,000 passengers in a single day, a new high, and domestic air and high-speed rail traffic both increased by more than 20%, reflecting strong travel and international travel demand.

A California-based company produces 250 MWh of nickel-hydrogen batteries annually at its Changzhou factory in China, aiming for one GWh capacity by 2027.