Endesa has started repowering work on the Coriscada wind farm in the Galician municipalities of Mañón and Ortigueira, replacing 40 wind turbines from 1998 with 4 latest generation turbines of 7 MW each, increasing annual production from 47 to 83.9 GWh and reducing the visual impact, with an investment of 36.3 million euros and completion expected by March 2028.
AI-generated summary
The Coriscada wind farm, active since 1998 in the Galician municipalities of Mañón and Ortigueira, had 40 wind turbines with a total capacity of 24 MW and an annual production of 47 GWh. Endesa, Enel's Spanish subsidiary, is carrying out a repowering intervention to modernize the plant using advanced technologies.
Enel's Spanish subsidiary, Endesa, has started repowering work on the Coriscada wind farm, located in the Galician municipalities of Mañón and Ortigueira.
The peculiarity of the project lies in the fact that, by exploiting the group's ability to equip itself with the best technologies on the market, Enel will significantly reduce the number of wind turbines in its fleet.
Endesa communicates this.
The repowering interventions, which will be carried out through the company SPV Sistemas Energéticos Mañón Ortigueira SA (96% owned by Endesa, through its subsidiary Enel Green Power España, and 4% by INEGA), involve the dismantling of the 40 wind turbines active since 1998 (of different power but with a total capacity of 24 MW) and their replacement with only 4 turbines of latest generation of 7 MW each, for a total installed capacity of 28 MW (while maintaining a grid feed capacity of 24 MW).
Thanks to this intervention, which involves a total investment of 36.3 million euros and will be completed during 2027, it is further explained, Endesa will not only significantly reduce the visual impact of the park by reducing the number of wind turbines, but will also improve the technological level, making the plants more efficient and safe from an operational point of view. The park's annual production will almost double, going from 47 GWh/year to 83.9 GWh/year.
In some cases, decommissioned wind turbines will be reused as spare parts for other existing Endesa plants or sold to third parties, always guaranteeing their reuse and without generating waste, thus extending their life cycle and creating added value. The components that cannot be reused will be fully valorised and recovered. Similarly, the use of technologies entirely produced within the European Union was promoted for new turbines, thus contributing to maintaining employment in the euro area. It is expected that, once the repowering works are completed, the Coriscada wind farm will start the testing phase at the end of 2027, to enter fully into operation in March 2028.

The Italian Senate has definitively approved the enabling bill for the return to sustainable nuclear power with 81 votes in favour, 51 against and 7 abstentions. The law entrusts the Government with the task of issuing implementing decrees within 12 months to regulate the development of small modular reactors (SMR and AMR) and fusion, with voluntary application mechanisms for territories and safeguard clauses for the national industry.

The Italian energy debate focuses on mini-nuclear reactors (SMR and AMR). Unlike traditional reactors, these are modular, factory-assembled and transportable, but their large-scale commercial deployment is expected no earlier than 2035.

An Irena report, presented at Climate Week in New York, highlights that the world must double the rate of installation of renewables to reach the target of 11.2 TW by 2030, set by the COP28 Consensus.

In August, electricity demand in Italy reached a record 28.9 TWh (+16.5% on an annual basis), driven by exceptionally high temperatures. Despite the growth of renewables, the requirement was also covered by thermoelectric power and imports.

In August, electricity demand in Italy reached a historic record of 28.9 TWh, marking +16.5% compared to the same month in 2025. The exceptionally high temperatures drove consumption.

The Elettricità Futura association urges the release of 4 thousand 150 GW renewable projects, held back by local bureaucracy. It also proposes the use of fixed-price contracts and PPAs to protect families and businesses from energy market volatility.