In Hamburg, a railway construction project with the Sternbrücke has been completed. The completion date was met.
AI-generated summary
The Sternbrücke in Hamburg is a central junction in the rail network that was renovated after months of construction.
After months of construction, the first trains are rolling again on Hamburg's Sternbrücke. The new, four-track-wide railway bridge in Hamburg-Altona has been open to train traffic since the early hours of the morning, as Deutsche Bahn announced. In contrast to the logistics group's other construction projects, the work went almost smoothly despite major challenges. And the announced completion date was met.
The spectacular construction project had reached a crucial milestone just a few weeks ago: at the end of July, the 3,700-ton shell of the new bridge, which had previously been maneuvered as a prefabricated part through the urban canyons of Hamburg, was installed in a night-time operation. Since then, remaining work has been necessary around the clock in order to be able to put the bridge into operation on time.
The Sternbrücke is a central junction in Hamburg's rail network. Before the closure, around 900 regional and long-distance trains and S-Bahn trains ran over the four tracks every day. The first journeys over the new bridge were made by a regional train from Kiel and an ICE to Basel.
Dozens of traffic lights failed in Berlin in the morning. The cause is likely a fire in a substation in central Berlin following an explosion.

Passengers in Upper Bavaria have been waiting in vain for 26 years for the electrification of the railway line from Munich via Mühldorf to Freilassing. Promised by the federal government in 1991, the project is still a long time coming.
After an extended closure, train traffic is rolling over the new, around 3,700 tonne star bridge in Hamburg. While trains are running as scheduled again, underlying roads remain closed for the time being and the dimensions of the new building are controversial.
From October 2026, DB InfraGO will carry out a general renovation of the Lehrte–Berlin railway line. For the Altmark and Stendal, this means months of total closures, the elimination of ICE stops and replacement bus services.
The East branch of Autobahn GmbH carries out around 1,000 bridge tests every year in Saxony, Saxony-Anhalt and Thuringia. While most bridges are in good condition, GDR structures with special prestressing steel are inspected annually due to increased risks.
A two-week full closure for construction work begins on Friday on the busy railway line between Düsseldorf and Cologne. Long-distance, regional and S-Bahn trains are being rerouted or replaced by buses; Some S-Bahn tracks even remain closed for months.